Final report for construction works
A final report is prepared by the contract administrator at the end at the end of the defects liability period once all defects have been rectified.
The final report should provide a summary of activities during the construction phase, describing:
- The works that have been completed.
- The variations that have been agreed.
- Claims for loss and expense or extension of time that have been agreed.
- The original contract sum.
- The final account.
- The completion date.
It is useful if both parties to the contract sign off the financial aspects of the report as representing the full and final settlement for the contract.
It can also be useful to prepare an end of contract report that provides greater detail about the performance of the contractor and is a record that can be referred to in the future in the event of public scrutiny, legal proceedings or if a judgement is being made about whether to employ the contractor again. See end of contract report for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.