Final report for construction works
A final report is prepared by the contract administrator at the end at the end of the defects liability period once all defects have been rectified.
The final report should provide a summary of activities during the construction phase, describing:
- The works that have been completed.
- The variations that have been agreed.
- Claims for loss and expense or extension of time that have been agreed.
- The original contract sum.
- The final account.
- The completion date.
It is useful if both parties to the contract sign off the financial aspects of the report as representing the full and final settlement for the contract.
It can also be useful to prepare an end of contract report that provides greater detail about the performance of the contractor and is a record that can be referred to in the future in the event of public scrutiny, legal proceedings or if a judgement is being made about whether to employ the contractor again. See end of contract report for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Government approach could undermine delivery and regeneration.
World's first mass timber data centre.
The overlooked environmental aspect of data centre development.
Introduction to radon awareness
New technical information sheet published by CIOB.
Updated supplier guide can help electrical contractors engage with NHP.
CIAT confirm the winners of the 2026 architectural technology awards.
Government launches a one stop shop for flood preparedness.
Sir Edwin Lutyens: Britain's greatest architect? Book review.
CIOB publishes free template to help assess and manage risks.
ECA's reflections on Party Conference season
Burnham wants to be confident of winning before asking for a fresh mandate.
New Chief Construction and Scientific Adviser
Sergio Cavalaro, Professor of Infrastructure Systems at Loughborough University.
Building safety levy for England
CIAT publish estimator tool for members.
Water sector faces a growing crisis that could slow the delivery of vital infrastructure.