End of contract report
Once the defects liability period has ended and the final account has been agreed, it is advisable for the contract administrator or construction manager to prepare an end of contract report (or post contract report). In the case of the construction manager this should be completed for each trade package. On a traditional contract it is a commentary or overview of the history of the main contract.
An end of contract report can be useful for a number of reasons:
- In the public sector, the politics of public scrutiny can lead to questions of audit, proprietary and transparency long after the project is completed.
- On all projects unanticipated legal proceedings can require the history of a project to be examined.
- It can provide a useful reference document chronicling the contractor’s performance. This can be helpful when considering whether to employ that contractor again.
An end of contract report may include the following:
Contractor design obligations and performance:
- Progress against programme.
- Adherence to design intent.
- BIM competency.
- Co-ordination with others in relation to things such as setting out and interfaces.
- Statutory approvals and independent design checks.
- Design faults.
- Variations.
- Resources employed.
- Off site engineering pre-payments.
- Progress against programme.
- Manufacturing errors, omissions or faults.
- Variations and scope reductions or increases.
- Percentage of work against factory output.
- Resources employed (machinery and labour).
- Suppliers and subcontracts.
- Offsite payments.
- Management resources.
- Progress against programme (delays, productivity and earned value analysis).
- Site co-ordination and efficiency.
- Labour or material shortages.
- Subcontractor performance.
- Industrial action.
- Plant (hired or owned).
- Progress photographs and installation records.
- Mock ups, samples and testing.
- Unacceptable work and quality ratings.
- Variations.
- Protection of installed work.
- Handover documentation.
- Defects and snagging.
- Weather / force majeure.
- Final account evaluation against contract sum.
- Contingency expenditure.
- Contractual warning notices of delay or disruption.
- Extensions of time.
- Details of claim applications, evaluations and settlements.
- Counter claims and liquidated and ascertained damages.
- Dispute proceedings.
- Performance bond.
- Collateral warrantees, guarantees and insurances.
- Insurance claims.
- Copy of any supplemental or wrap up agreements.
- Copy of signed contract documents and post tender minutes.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
Level 6 Design, Construction and Management BSc
CIOB launches first-ever degree programme to develop the next generation of construction leaders.
Open for business as of April, with its 2026 prospectus and new pipeline of housing schemes.
The operational value of workforce health
Keeping projects moving. Incorporating unplanned absence and the importance of health, in operations.
A carbon case for indigenous slate
UK slate can offer clear embodied carbon advantages.
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.






















