End of contract report
Once the defects liability period has ended and the final account has been agreed, it is advisable for the contract administrator or construction manager to prepare an end of contract report (or post contract report). In the case of the construction manager this should be completed for each trade package. On a traditional contract it is a commentary or overview of the history of the main contract.
An end of contract report can be useful for a number of reasons:
- In the public sector, the politics of public scrutiny can lead to questions of audit, proprietary and transparency long after the project is completed.
- On all projects unanticipated legal proceedings can require the history of a project to be examined.
- It can provide a useful reference document chronicling the contractor’s performance. This can be helpful when considering whether to employ that contractor again.
An end of contract report may include the following:
Contractor design obligations and performance:
- Progress against programme.
- Adherence to design intent.
- BIM competency.
- Co-ordination with others in relation to things such as setting out and interfaces.
- Statutory approvals and independent design checks.
- Design faults.
- Variations.
- Resources employed.
- Off site engineering pre-payments.
- Progress against programme.
- Manufacturing errors, omissions or faults.
- Variations and scope reductions or increases.
- Percentage of work against factory output.
- Resources employed (machinery and labour).
- Suppliers and subcontracts.
- Offsite payments.
- Management resources.
- Progress against programme (delays, productivity and earned value analysis).
- Site co-ordination and efficiency.
- Labour or material shortages.
- Subcontractor performance.
- Industrial action.
- Plant (hired or owned).
- Progress photographs and installation records.
- Mock ups, samples and testing.
- Unacceptable work and quality ratings.
- Variations.
- Protection of installed work.
- Handover documentation.
- Defects and snagging.
- Weather / force majeure.
- Final account evaluation against contract sum.
- Contingency expenditure.
- Contractual warning notices of delay or disruption.
- Extensions of time.
- Details of claim applications, evaluations and settlements.
- Counter claims and liquidated and ascertained damages.
- Dispute proceedings.
- Performance bond.
- Collateral warrantees, guarantees and insurances.
- Insurance claims.
- Copy of any supplemental or wrap up agreements.
- Copy of signed contract documents and post tender minutes.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.