Wembley Stadium
Contents |
[edit] Introduction
Wembley Stadium is the largest stadium in the UK and the second-largest in Europe, with a capacity of 90,000. Completed in 2007, it was built on the site of the original stadium which dated back to 1923 and that with its ‘twin towers’ was perhaps the most famous in the world. Designed by HOK Sport and Foster + Partners, the new stadium is recognisable by its 134 m (440 ft) high steel arch that supports most of the weight of the sliding roof.
[edit] Original stadium
In 1920, a major Exhibition was announced for London to promote trade throughout the British Empire. The then-Prince of Wales, who was also President of the Exhibition’s organising committee, was keen that the scheme should include ‘…a great national sports ground’, and accordingly, land was purchased at the vacant Wembley Park pleasure gardens. The Football Association (FA) had been looking for a venue to host their Cup Finals and so became interested in the project.
A design was prepared by Sir John Simpson and Maxwell Ayrton, using the new material of ferro-concrete. Sir Robert McAlpine & Sons began work on the Exhibition site in early-1922, once the £750,000 funding had been raised. The domed twin towers were built in situ, 126 ft high, surmounted by concrete flagstaffs capped by concrete crowns.
The stadium construction was completed in April 1923, a year before the British Empire Exhibition was opened by King George V. After the exhibition, developer Jimmy White offered £300,000 for it, with the plan being to demolish it. One of the demolition sub-contractors Arthur Elvin eventually bought White out and became Managing Director of the Wembley Stadium and Greyhound Racecourse Co.
With its survival ensured, the stadium later became the centerpiece of the 1948 Olympic Games, and it has continued to stage major sporting and musical events since then. Most notably, it hosted the 1966 World Cup Final and one of the Live Aid concerts in 1985.
The last football match was played at the stadium on 7 October 2000.
[edit] New stadium
In 1996, the Sports Council decided to base a new English National Stadium at Wembley, retaining the globally-recognised name. It was decided that the original stadium no longer met the standards in terms of facilities that were expected at a major venue. In 1999, the stadium was bought by Wembley National Stadium Ltd. for £103m.
Despite the iconic status and Grade 2 listing of the twin towers, their demolition was approved by Brent Council as necessary in terms of the overall project.
The World Stadium Team Consortium appointed Foster + Partners and HOK Sport to design the stadium, and Australian company Multiplex were awarded the role of contractor.
Despite being scheduled to begin before the end of 2000, the demolition works were delayed by financial and legal difficulties, eventually beginning in mid-2002. By this point the project had become part of a much wider regeneration plan that would see the development of Wembley Park and the surrounding area over the next 2 decades.
The towers were dismantled in February 2003, with the rubble being used as part of the new stadium’s foundations. The foundations were formed by 4,000 separate piles, the deepest of which is 35 m (115 ft). In total, 90,000 m3 of concrete and 23,000 tonnes of steel were used in the construction.
As part of the works, the level of the pitch was to be lowered by 4 m from the original. During this process, excavators discovered the concrete foundations of Watkin’s Tower which had been an attempt to create an English version of the Eiffel Tower that was abandoned at base level in 1907 before being demolished for the construction of the original stadium.
In May 2004, the iconic steel arch was lifted into place, weighing 1,750 tonnes, with a 7.4 m diameter and a 315 m span. It is currently the largest single roof structure in the world and supports the weight of the north roof as well as 60% of the south roof.
Numerous issues beset the project as it ran further behind schedule. In 2006, a steel rafter fell by a foot-and-a-half which forced the evacuation of 3,000 workers. A few weeks later, sewers beneath the stadium buckled due to ground movement resulting in repairs that required several months to undertake.
However, despite missing several deadlines and being mired in controversy, the stadium finally opened in 2007.
[edit] Litigation
The contractors Multiplex originally agreed to build the stadium for £326.5m. However, they made significant losses on the project, the final cost of which was £798m.
Subsequently, Multiplex tried to raise a number of legal cases against sub-contractors and consultants in an attempt to recoup some of their losses, including the original steel contractor Cleveland Bridge. One of these was the largest construction claim in British legal history, against the structural engineering consultants Mott MacDonald for £253m. With legal fees threatening to spiral out of control, the case was eventually settled out of court in June 2010.
[edit] Project data
- Owner: The Football Association.
- Operator: Wembley National Stadium Ltd.
- Capacity: 90,000
- Construction start: 2002.
- Construction completed: 2007.
- Cost: £757m.
- Architects: HOK Sport, Foster + Partners.
- General contractor: Multiplex.
[edit] Related articles on Designing Buildings Wiki
- Beijing National Stadium.
- BT Tower.
- Building of the week series.
- City Hall, London.
- Gateway Arch.
- London 2012 Olympic Stadium.
- Maracana Stadium.
- Millennium Dome.
- Norman Foster.
- Olympic Stadium, Montreal.
- Roman Colosseum.
- Stadium.
- Stamford Bridge stadium.
- Sydney Opera House.
- Thames barrier.
- The Gherkin.
- The Shard.
- Unusual building design of the week.
- Wembley Arena.
- Wembley Park.
[edit] External references
- Wembley Stadium - Official site
Featured articles and news
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.