Tender documentation for construction projects
Contents |
[edit] What are tender documents?
A tender is a submission made by a supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. Tender documents are prepared to seek offers from potential suppliers. Tender documents may be prepared for a range of contracts, such as equipment supply, the main construction contract (including design by the contractor), demolition, enabling works, and so on.
[edit] Why should tender documents be broken down into packages?
Ideally, tender documents should be broken down into a series of packages (even if there will only be one main contract) each with its own design drawings and specifications suitable to be issued by the tier 1 supplier (often the main contractor) to potential sub-contractors. This makes the tender easier for the contractor to compile and price and easier for the client to compare with other tenderers.
It is important, when this is done, to ensure that the interfaces between packages are properly identified and clearly allocated to one package or another. Having too many packages increases the number of interfaces and so the potential problems. The cost plan (pre-tender estimate) should also be re-assembled package by package to allow easy appraisal of tenders received.
[edit] What should tender documents include?
Tenders documents will vary depending on the nature, size and complexity of the contract, but tender documents for the main construction contract will typically include:
- A letter of invitation to tender.
- The form of tender (a formal acknowledgement that the tenderer understands and accepts the terms and conditions of the tender documents and any other requirements that are stipulated). For more information see: Form of tender.
- Preliminaries: including pre-construction information and site waste management plan (if required). Preliminaries provide a description of a project that allows the contractor to assess costs which, whilst they do not form a part of any of the package of works required by the contract, are required by the method and circumstances of the works. For more information see: Preliminaries.
- The form of contract, contract conditions and amendments. For more information see: Form of contract.
- A tender pricing document (or contract sum analysis on design and build projects). This sets out the way in which the client wishes to review the breakdown of the overall tender prices provided.For more information see: Tender pricing document.
- Employer's information requirements for BIM. Defining the information that will be required by the client from suppliers for the development of the project and for the operation of the completed built asset. For more information see: Employer's information requirements
- Design drawings, and perhaps an existing building information model.
- Specifications describing the products, materials, and work required.
- Tender return slip. A label that is fixed to the tender for it to be returned to the tenderer. It will usually state that it is not to be opened before a certain time and date. The return slip can also include the title of the contract, the return address, a tender checklist and instructions for the tenderer.
Copies of the tender documentation should be kept for records.
See also:
NB: On construction management contracts, tender documentation for trade contracts might include the construction manager's master programme.
It is good practice to send relevant documents direct to sub-contractors named in bills of quantities and to tell tendering contractors that this has been done, so they know they do not have to.
[edit] Related articles on Designing Buildings
- Invitation to tender for construction contracts
- Form of tender
- Typical tender process for construction projects
- Specification for construction
- Tender pricing document
- How to prepare tender documents
- Tender processes for construction contracts
- Construction contract
- Preliminaries in construction
- Design drawings
- Bill of quantities BOQ
- Construction contract conditions
- Main contract.
- Employer's information requirements EIR
- Contract documents for construction
- Pre-construction information
- RFx.
- Tender submission.
- Tender works programme
- Pre qualification questionnaires and PAS 91.
- Pre-tender estimate for contracts
- Construction work packaging
- Bid writer
[edit] External references
- CPIC the Construction Project Information Committee, responsible for providing best practice guidance on the content, form and preparation of construction production information.
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
1) What are the alternative tender pricing documentation formats used for different procurements available.Also in your opinion and experience what are the advantages and disadvantages of each type?
Answering this question is not straight forward and would take a lot of research.
There are number of articles on the site that might be useful to you, in particular; Contract sum analysis, Tender pricing document and Schedule of rates. Others may also be of interest, such as; Bills of quantities, Pre-tender estimate, Measurement contract, Procurement route and so on.
Sorry not to be of more help.
2) In which tender package (TP) would one put "Sliding automatic doors"? Is it Electromechanical (EM), like lifts and escalators? Who specifies them? The architect or the EM engineer?
Generally we would expect them to be in their own separate package with the builders work in the electrical package. Specified by the architect probably using a closed specification based on a preferred manufacturer.
3) Is there a publication of some sort that associates 'work results' (WR) with the corresponding generally expected TP? (although one realises that the allocation of WRs to TPs is to some degree project specific).
Not to our knowledge. A good client team ought to provide tender feedback to unsuccessful bidders.
4) What are the advantages and disadvantages of including detailed information in a tender document on the types of inspections the Engineer will carry out on the Contractor's workmanship and marterials?