Suppliers for design and construction
In the construction industry, ‘supplier’ (or economic operator) is a very general term which refers to organisations contracted as part of the delivery of a built asset.
Traditionally, suppliers might have been considered to be organisations contracted to provide physical supplies such as goods, materials, plant, and so on, however, its use is now much broader and PAS 1192-2 (now replaced by BS EN ISO 19650) defines a supplier as any ‘…provider of services or goods either directly to the employer or to another supplier in a supply chain’. The 'supply chain' is the interconnected hierarchy of suppliers.
As construction has become more complex, and suppliers have become more specialist, so the supply chain has extended. On a straight-forward 'traditional' building project, design consultants and the main contractor, sometimes referred to as tier 1 suppliers, work for the employer, and the main contractor may have a limited chain of their own suppliers.
However, on PFI or design and build projects, there may be just one first tier, or principal supplier, with wide range of consultants, sub-consultants, and sub-contractors working for them. The situation becomes more complicated on large projects when the employer has several tier 1 suppliers, all with extended supply chains. This may cascade down to a plethora of suppliers sometimes unknown to management at the top of the chain.
One of the difficulties encountered in the construction industry is that the first and second tier of the supply chain often sign-up to fairly onerous contract conditions but as the chain develops, so the contractual liabilities decrease until suppliers at the end of the chain may not be ‘locked in’ at all.
BIS Research paper No. 145, Supply Chain Analysis into the Construction Industry, A Report for the Construction Industrial Strategy, published by the Department for Business Innovation and Skills in October 2013 assessed five projects ranging in value from £1 million to £25 million.
It defined suppliers as:
The report suggests that, ‘Tier 1 contractors are typically termed main contractors, and many tier 2 contractors are described as specialist contractors. Labour-only sub-contractors typically operate at the third tier.’
It found that it was not uncommon to have 50 to 70 tier 2 suppliers and sub-contractors and suggested that the, ‘…duplication of multiple layers of profit, overhead and risk could represent a source of non-value added cost and waste.’
In recent years, larger employers offering continuity in construction have taken an increasing interest in establishing relationships beyond direct, first tier suppliers. Framework contracts and partnering agreements have pioneered this approach, encouraging the involvement of selected suppliers at relatively early stages of projects while offering continuity of work. This has led to greater collaboration between lead designers, contractors, specialist designers and specialist suppliers.
[edit] Related articles on Designing Buildings
- Code for Construction Product Information CCPI.
- Contractor vs supplier.
- Critical service contracts.
- Critical suppliers.
- Fragmentation of the UK construction industry.
- Indirect supplies.
- Integrated supply team.
- Key suppliers.
- Main contractor.
- Manufacturer.
- Named specialist work.
- Nominated supplier.
- Novation.
- PAS 1192-2.
- Partnering.
- Point of supply.
- Products v goods v materials.
- Public sector dependent suppliers.
- Reserved contract.
- Service provider.
- Spark framework RM6094.
- Subcontractor.
- Supply.
- Supply chain integration.
- Supply chain management.
- Tier.
- Tier 1 suppliers.
- Tier 2 and tier 3 suppliers
- Types of contractor.
- VAT reverse charge.
[edit] External references
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.