Novation
Contents |
[edit] Introduction
Novation is a process by which contractual rights and obligations are transferred from one party to another. Whilst the benefits of a contract can be transferred by assignment, if the parties wish to transfer both the benefits and the burdens then this must be done by a novation agreement.
A novation occurs when there is a rescission of one contract and the substitution of a fresh contract in which the original contractual obligations are carried out by different parties. In building design and construction, novation normally refers to the process by which design consultants are initially contracted to the client, but are then 'novated' to the contractor.
This is common on design and build projects where the design team are appointed by a client to carry out initial studies or prepare a concept or detailed design, but then when a contractor is appointed to carry out or complete the design and construct the works, the design team (or part of it) is novated to work for them.
This can be beneficial to clients as it maintains continuity between pre-tender and post-tender design whilst leaving sole responsibility for designing and building the project with the contractor. Novation effectively over-writes the contractual history to give the impression that the consultant has worked for the contractor throughout the project
NB. The process of novation in itself does not make a contractor responsible for any design carried out for the client prior to novating their contract. To achieve this the building contract needs to specifically state that the contractor has examined the design and adopted it.
[edit] Documentation
A novation agreement is not possible without consent. If novation and the form of novation agreement were not agreed when the consultant’s was initially appointed, they are under no obligation to agree to be novated. It is essential therefore that the principal contracts between client and consultants and between client and contractors contain express terms obliging the contractor and the consultant to enter into the novation agreement.
To avoid the risk of merely having an agreement to agree which is unenforceable, a specimen form of the proposed novation agreement should be appended to the original contractual documentation.
It is important that any novation documentation is properly drawn up and that it makes clear which services consultants performed for the client and which they will now perform for the contractor, otherwise initial appointment agreements may be rendered meaningless, for example a requirement for the consultant to inspect the contractor's work and report to the client (when they are in fact now appointed by the contractor).
The process of novation can leave designers feeling they have mixed loyalties and there can be difficulty determining where liability lies for design work carried out before novation. If the contractor does not take on the design team effectively as if they had been the employer from the beginning therefore, it may be wise for them to obtain warranties for pre-novation services from the designers. The client may also require collateral warranties from novated designers (see Blyth & Blyth Ltd v Carillion Construction Ltd).
[edit] Consultant switch
As an alternative to novation, there may be a 'consultant switch', which simply transfers the consultants from working for the client to working for the contractor, without altering the contractual history.
When there is a consultant switch, the original agreement between the consultant and the client terminates on appointment of the contractor, and there is then a new agreement between the contractor and the consultant.
This can be seen to provide better clarity of the contractual relationships. However, because the consultant’s liability to the client for pre-switch services remains, some argue that there is a greater risk of conflict of interest.
For more information see: Consultant switch.
[edit] Related articles on Designing Buildings
- Architect.
- Appointing consultants.
- Assignment.
- Assignment of debt.
- Blyth & Blyth Ltd v Carillion Construction Ltd.
- Collateral warranties.
- Concept design.
- Consultants.
- Consultant switch.
- Designers.
- Design and build.
- Design and build - pros and cons.
- Detailed design.
- Difference between assignment and novation.
- Joinder.
- Privity of contract.
- Procurement route.
- The Contracts (Rights of Third Parties) Act.
[edit] External references
- PACE Guidance on the Appointment of Consultants and Contractors P126 guidance on novation.
- Building article: Novation without tears.
- KPK Research, Design and build, novation or consultant switch?
Featured articles and news
A transformative shift in the design, construction and management of built assets.
Apprenticeship announcement by the Prime Minister
Welcomed but with call for more actionable detail.
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach 7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Comments