Difference between assignment and novation
Transferring an interest in a construction contract from one party to another can be done by either assignment or novation. The differences are minimal but important to understand, as the assignment of an interest when it could be novated might render one party liable for the contract if the other party is unable to perform their obligations.
Assignment is the right to transfer 'choses in action' defined as 'all personal rights of property which can only be claimed or enforced by action and not by taking physical possession'. This definition includes benefits arising under a construction contract such as right to payment, but not burdens such as the obligation to pay. The definition also includes claims for breach of contract.
A common error is to assume that the right to assign must be agreed as part of a contract, like a novation. Assignment is a unilateral right created by statute, Section 136 of The Law of Property Act 1925 or by the law of equity (law developed by the Chancery Division of the High Court of England and Wales). However, the right to assign can be excluded, or restricted, by contract, for example, it is common in collateral warranties to restrict to one assignment without the written permission of the warrantor.
By comparison, novation is a process in which the contractual rights and obligations are transferred to a third party. The benefits and the burdens can be transferred by a novation agreement, rather than just the benefits as with assignment. In building design and construction, novation normally refers to the process by which design consultants are initially contracted to the client, but are then 'novated' to the contractor.
[edit] Related articles on Designing Buildings
- Alienation covenant.
- Assignment.
- Assignment of choses in action.
- Assignment of debt.
- Collateral warranties.
- Difference between collateral warranties and third party rights.
- Legal and equitable assignment.
- Novation.
- Novation agreement.
- Privity of contract.
- Restrictions on assignment.
- Reverse premium.
- The Contracts (Rights of Third Parties) Act.
Featured articles and news
ICE Trustee Board update June 2022
Given by ICE President Ed McCann.
Artificial intelligence and project management
Two new research reports published by APM.
Association for Project Management membership offer
50% off APM Associate membership for Designing Buildings users.
Building safety, a shifting landscape for professionals
A commentary from the insurance perspective.
In brief with further links.
Walter Segal: self-built architect
A definitive book on a pioneer of green architecture.
Funding for heritage on the high street
Using heritage as a catalyst for reviving historic centres.
Commonwealth Heads of Government Meeting update.
Declaration prioritising sustainable urbanisation adopted.
A small hidden, often distant but key building component.
Some brief words about the actuator.
CIAT Chief Executive steps down.
After 34 years at the Institute.
Volunteer opportunity launched by the ICE
To support the next generation of engineers.
Provisional findings show illegal cartels in the industry.
CIAT reporting from the Competition and Markets Authority.
Making sustainable construction number one priority.
The future of construction report.
Interview with ECA CEO.
Many provisions came into force on June 28, 2022.
With room to expand.
An information packed session at the BSRIA conference.
Refurbishment, Energy Efficiency, Indoor air and process.
Create a profile, write informed product articles and share.
Aluminium Composite Panels (ACP) is one example.
We are indeed now 10 years old, so go on and be bold !
Write about something you know, help us build and grow !
Comments