Pre-tender estimate for contracts
The pre-tender estimate (PTE) is the final estimate of the likely cost of the works that are described in completed tender documents prepared to seek tenders (offers) from prospective suppliers. The pre-tender estimate itself is not included in the tender documents.
It provides a final comparison with the budget, and along with the cash flow estimate enables the client to confirm that sufficient funds are available before committing to seeking tenders.
It also gives a basis for assessing and comparing tenders when they are returned.
If the pre-tender estimate exceeds the approved budget, an explanation should be provided for the client to consider and issue instructions.
As with the tender documents, the pre-tender estimate should be broken down into a series of packages (even if there will only be one main contract), this will allow easy appraisal of tenders received, which are likely to prepared by contractors based on prices of packages received from sub-contractors. It ensures that the tenders are easily compared with one another and with the pre-tender estimate, and any anomalies or potential savings identified.
The pre-tender estimate should be prepared following a standard approach to estimating such as that defined by the new rules of measurement (NRM).
NB: A post tender estimate is '…a cost estimate carried out after the evaluation of tenders to corroborate the funds required by the employer to complete the building project.' For more information, see Post tender estimate.
[edit] Related articles on Designing Buildings
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Business plan.
- Cash flow projection.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Estimate.
- Estimator.
- Final account.
- Front-loaded costs.
- Initial cost appraisal.
- New Rules of Measurement.
- Order of cost estimate.
- Post tender estimate.
- Tender pricing document.
Featured articles and news
The end of the games but continued calls for action.
From the Commonwealth Association of Architects.
CIOB respond to the government call for evidence
For the Levelling Up, Housing & Communities Committee.
How are buildings and their occupants responding to extreme heat?
BSRIA's Technical Director reflects on recent weather patterns.
Landownership in England in 1909
A national valuation to fund old-age pensions.
The world’s largest Commonwealth memorial to the missing.
Long after the end of the defects liability period.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing in buildings.
Geometric form and buildings in brief
From the simple to the complex.
Understanding the changing nature of insulation
And the UK Government guidelines.
Three year action plan to improve equity, diversity and inclusion
Commitment agreed to by major built environment bodies.
The Construction Route – what needs to change?
Electrical skills, low carbon, high-tech and the building services revolution.
Deep geothermal power possibilities
Ultra-deep drilling with millimeter-wave beam technology.
BSRIA Briefing 2022- From the outside looking in
Looking at the built environment from space.
Competence requirements for principal contractors and designers
BSI standards 8671, 8672 and 8673.
Bringing life to burial grounds.
From failed modernism to twenty-minute neighbourhoods.
Design chill and design freeze
The gates process and change control.
Neuroscience for project success
Why people behave as they do. APM book.
Comments
what is cost reconciliation and why is there one on all submitted tenders is required before placing a contract.