Due diligence when selecting contractors or subcontractors
Contents |
[edit] Introduction
The financial failure of a contractor or key supplier can be catastrophic to a project.
To reduce exposure to risks it is important to have a thorough grasp of both the capability and financial status of a prospective organisation before appointing them.
Reliance on credit checks involving accounts filed at Companies House can be useful, as can assessments of past track record, but they have their limitations. It is important to understand where the organisation might be exposed to risks through commitments to, or reliance on, third parties, and how secure and well resourced they are given the size of the proposed contract and their other commitments.
The following issues should be evaluated against the proposed scope of works to be undertaken:
[edit] History
- Track record and appropriate references.
- Audited accounts.
- Tax returns.
[edit] Current position
- Main customers (each expressed as a percentage of total turnover to reveal where there may be significant dependencies).
- Current contracts in progress including project programmes and values (to assess where there may be significant overlaps that would put the organisation under pressure).
- Staff resources and CV’S of senior management.
- Organisation chart.
- Current debt position with debt expiry dates.
- Current direct labour resource, including comparisons with previous years.
- Current subcontractors and suppliers.
- Details of current warrantees, guarantees, encumbrances, liens, performance or on-demand bonds or charges held by third parties.
[edit] Future position
- Pipeline work under tender or negotiation.
- Current unaudited annual accounts in progress.
- Proposed subcontractors and suppliers.
[edit] Legal position
- Litigation, claims and other disputes in progress.
- Ownership of intellectual property, patents, licenses and certification required to carry out the work.
- Insurances in place.
- Partnerships or joint ventures with other organisations.
- Ownership of machinery and facilities required to execute the work.
[edit] Technical capability
- Examination of past or current similar work.
- Competency, qualifications and certificates.
- Subcontractor and supplier capability.
- Building Information Modelling (BIM) capability.
- Overall capacity to undertake the work.
- Disaster planning in the event of a catastrophic occurrence such as fire.
[edit] Other indicators
- The cost of performance bonds.
- Reputation in the insurance market.
- Time taken to pay subcontractors and suppliers.
[edit] Step-by-step guidance on appointing a contractor:
- Traditional contract: tender.
- Design and build: tender.
- Construction management: tender.
- Management contract: tender.
- Public project: tender.
[edit] Related articles on Designing Buildings
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.