Public project: tender
Tendering is the process of selecting and appointing an integrated supply team for the main contract.
The Government Construction Strategy proposes that publicly-funded projects adopt either a design and build, private finance initiative (PFI) or prime contract procurement route. These routes involve contracting an integrated supply team to design, construct and sometimes finance, operate and maintain the development. Traditional procurement routes that separate design and construction should not be used unless it can be demonstrated they offer better value.
Depending on how experienced the client is, they may appoint external consultants such as independent client advisers or a project manager to assist them.
Contents |
[edit] Starting the work stage.
The client updates the project execution plan to reflect comments made at the end of the previous stage.
The client may wish to appoint additional independent client advisers, a project manager or contract administrator. Go to work stage: Public project: appointment.
The client arranges a stage start-up meeting with the internal client team, independent client advisers and project manager (if appointed) to issue any amendments to the project execution plan, confirm the procurement route and to agree the programme and procedures that will be adopted for tendering. The client gives instructions relating to lists of approved contractors, OJEU requirements, preferred form of contract, contract conditions, the allocation of risk and the appointment of the contract administrator (or employer's agent). The contract administrator (if appointed) discusses with the client their delegated limit for issuing instructions in relation to the contract.
The client prepares selection criteria for the integrated supply team and pre-qualification questionnaires (The Government Construction Strategy suggests that PAS 91 should be used).
If it is necessary and has not already been done, OJEU or other adverts are prepared and placed.
- Public sector contracts may subject to fair payment practices.
- Public sector contracts may be subject to requests under the Freedom of Information Act.
- Public sector contracts are increasingly likely to include requirements for building information modelling (BIM). This may affect consultants’ appointments, pre-construction services agreements, the main contract and sub-contracts in relation to the supply of design information and ‘as built’ or ‘as manufactured and installed' information.
[edit] Preparing the tender documentation.
If it has not already been done, the client develops the project brief into an output-based specification. They then select the form of contract and contract conditions (perhaps with advice from independent client advisers and project manager if there is one) and co-ordinate the preparation of tender documentation.
The client co-ordinates the preparation of pre-construction information (perhaps with help from the principal designer if the client has appointed one), and if it has not already been done, the client prepares or arranges for the independent client advisers to prepare a site waste management plan (if required).
The client prepares (or arranges for the preparation of) a pre-tender estimate, cash flow projection and tender pricing document (or contract sum analysis), then co-ordinates a review of the tender documents and makes amendments if necessary.
The client instigates change control procedures for the tender documents and arranges printing of the tender documents.
[edit] Identifying potential tenderers.
From responses received to any adverts placed, or from recommendations received, the client co-ordinates the preparation of a long list of potential tenderers. The client then issues pre-qualification questionnaires to the long list of potential tenderers.
The client receives completed pre-qualification questionnaires from the long list of potential tenderers.
The client carries out financial checks on potential tenderers (ideally the contract should not be more than 20% of the annual turnover of the potential tenderers) and considers potential tenderers' competence as principal contractor.
The client co-ordinates any advice from independent client advisers, the project manager and internal client team on prospective tenderers and prepares an initial short list of tenderers. They then arrange pre-tender interviews with the initial short list of tenderers.
If necessary, following comments received during the pre-tender interviews, the client co-ordinates amendments to the tender documentation and prepares a final short list of tenderers.
[edit] Identifying the preferred tenderer(s).
The client collates tender documents (including the output-based specification) and arranges for its dispatch to and return from the tenderers. They then compile queries from tenderers and co-ordinates responses which should be issued to all tenderers. If necessary, the client arranges mid-tender interviews and / or site visits for the tenderers.
If queries from the tenderers or discussions during the mid-tender interviews result in significant clarification of, or changes to, the tender documentation, the client may wish to extend the tender period.
The client receives the tenders. They may follow a formal procedure for opening and recording tenders. The client then co-ordinates assessment of the tenders (including assessments by any independent client advisers). This may include further interviews.
The client selects and enters into negotiations with the preferred tenderer(s). A reserve tenderer may be retained in the event that negotiations with the preferred tenderer are unsuccessful.
[edit] Entering into negotiations with the preferred tenderer(s).
The client co-ordinates negotiations with the preferred tenderer(s). Negotiations may be led at different stages by the client's in-house team, independent client advisers, a contract administrator or by a project manager. This process of negotiation may involve development of, or changes to, any design proposals prepared by the tenderers to ensure a best value solution is adopted. NB It is paramount in any negotiation that the individuals negotiating either have authority to fully negotiate terms, or make it clear from the start the limits to their authority. This may mean re-convening with the right people empowered to make decisions.
The client co-ordinates the preparation of a tender report and if necessary makes changes to the tender documents and requests a revised tender from the preferred tenderer(s).
[edit] Gateway review 3: investment decision.
The senior responsible owner (SRO) commissions an independent peer review of the project: gateway review 3: investment decision, which re-assesses the business case and governance arrangements prior to the decision to invest. Gateway reviews are mandatory for central civil projects and best practice for the health sector, local government and defence projects.
The review team issue a confidential review report to the senior responsible owner who then implements any actions necessary.
The senior responsible owner confirms that funding is available and that there is still stakeholder support for the project.
The investment decision maker (IDM) considers whether to proceed to contract the preferred tenderer.
[edit] Appointing the integrated supply team.
The client collates the contract documents and arranges for the printing (engrossment) and execution of two copies, one for the client to retain and one for the preferred tenderer (from hereon called the integrated supply team). Alternatively, the client might retain one executed contract, with certified copies being issued to the integrated supply team, this can avoid potential errors in preparing two contracts for execution. The integrated supply team may be required to provide a performance bond, warranties and evidence of insurance cover.
If appropriate, the client arranges for copies of the contract documentation (or relevant parts) to be issued to independent client advisers, contract administrator and the project manager.
The client informs other tenderers that they have been unsuccessful.
Featured articles and news
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.