Ground energy options
Contents |
[edit] Introduction
Below a depth of approximately 6m, the temperature of undisturbed ground remains fairly constant at the mean annual air temperature throughout the year. Depending on the location and depth this temperature is typically between 9 and 12ºC in the UK. This means that the ground can be used to as a heat source in the winter and as a source of coolth in the summer.
In general, the use of ground energy to provide heating and cooling in buildings requires equipment (heat pumps). The energy can be transferred to this equipment using a ground heat exchanger (closed loop system). This usually comprises a number of pipe loops, vertical or horizontal, with a primary process medium of water, or more normally a glycol solution which eliminates the possibility of freezing at the lower end of the application’s seasonal temperature range. An alternative system is to abstract and discharge ground water (open loop systems) from an aquifer beneath the building.
In the case of the closed loop system, the energy in the ground is (if the ground loop is sized appropriately) replenished by solar irradiation, rain and, sometimes, for deeper vertical collector systems, underground water flow. With open loop systems it is necessary to consider the sustainable yield available from the wells.
[edit] Variations of ground energy
[edit] Horizontal – closed loop
With this variation, the energy or heat is transferred to the building using a series of ground collectors, laid horizontally at a depth of 1.5-2m. Each pipe run should be limited to 100m to avoid the need for more powerful circulation pumps. Pipe runs would normally be the same length to guarantee similar flow conditions, pressure drops and to ensure an even heat extraction from the ground.
The useable amount of heat or energy is dependent on the following:
- Solar irradiation for the specific area.
- Moisture content.
- Soil type.
- Size of pores.
Extraction rates are generally in the order of 10 W/m2 for dry sandy soil, to over 30 W/m2 for wetter loamy soils. Relatively inexpensive earth moving equipment is required for installation, although costs increase with greater depths. This type of collector is generally used for applications with lower power outputs where there is a large undeveloped area that is easy to excavate.
[edit] Vertical (probe) – closed loop
A vertical closed-loop system utilises vertical ground heat exchangers or probes that are inserted into specially drilled boreholes up to depths of 150m.
Extraction rates generally vary between 20 W/m for loose dry substrate to ~80W/m for damper sandstones, granites and basalts.
The useable heat or energy is dependent on similar factors to the horizontal system although more specialist geological analysis is generally needed. Deeper test-bores can ascertain the type and depth of each soil/rock layer, the heat transfer potential for the different layers over the length of the borehole, the presence and height of water table and underground water flow.
Due to the requirement for a test bore, this type of system lends itself to larger applications where the initial testing costs can be justified. The data gathered helps to reduce risk during the design stage as non-optimum sizing has serious cost implications.
[edit] Vertical – open loop
In this variation, ground water is extracted direct from the underground water aquifer, eliminating the need for a closed loop ground heat exchanger. The used cooled or heated water can then be returned to the ground via a return well.
Prior to the consideration of such a configuration, it is necessary to contact the Environmental Agency, initially to gain consent for a pumping test, then for a final abstraction licence for a pumping test, and finally for discharge consent. There is an additional requirement to consider the water quality of the water source, as this can have an adverse effect on the materials used within the heat exchanger.
[edit] Feasibility and Evaluation
[edit] Generic guidelines for ground energy systems
[edit] Start considering the technology at an early stage in the project.
- Complete a ground energy desktop survey to establish the suitability of the geology and hydrogeology underneath the site to different types of ground energy systems. Suitable sources include the British Geological Survey and site specific Geotechnical Investigation reports.
- Establish the spatial limitations around the building.
- What is the indicative foundation design and is it suitable to act as part of the ground energy heat exchanger?
[edit] Optimise the heating and cooling building circuits.
- Use high temperature cooling where possible (eg chilled beams and air based systems with over sized heat exchangers).
- Use low temperature heat emitters (large radiators, underfloor heating and air based systems with oversized heat exchangers).
- Simultaneous heating and cooling can be provided from the same heat pump unit.
[edit] Closed loop do’s
- For larger commercial systems, ie greater than ~100kW, a thermal conductivity test is advisable to confirm the insitu thermal properties.
- Carry out a desktop simulation using recognised software to ensure long-term performance can be guaranteed.
- Ensure boreholes are spaced adequately to reduce thermal interference.
- Try to balance heat abstraction and rejection to the ground.
- Consider using less expensive conventional plant for infrequent heating and cooling loads and/or higher relative seasonal heating and cooling loads.
[edit] Open loop do’s
- For almost all open loop systems, Environment Agency (EA) approval is needed for both abstraction and discharge of ground or surface water.
- A pumping test will be needed to confirm the yield and to get permission from the EA to abstract and discharge a specified volume of water per hour/day/year.
- Start the process to obtain an abstraction licence and discharge consent as early as possible, as this process can take eight to nine months in the UK.
This article was created by --Buro Happold, 17 March 2013, based on a 2008 article in 'Patterns'.
[edit] Related articles on Designing Buildings Wiki
- Dynamic thermal modelling of closed loop geothermal heat pump systems.
- Earth-to-air heat exchangers.
- Environmental performance.
- Geothermal energy.
- Geothermal pile foundations.
- Ground preconditioning of supply air.
- Ground source heat pumps.
- Heat gain.
- Heat pumps.
- Ring circuit.
- Thermal labyrinths.
- Water source heat map.
- Water source heat pump.
[edit] External references
Featured articles and news
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.


























