Management contract: mobilisation
Mobilisation refers to the activities that should be carried out after the works contractors have been appointed, but before they commence work on site. It is a preparatory stage during which the majority of activities are managed by the management contractor.
[edit] Preparing for the construction stage.
The management contractor arranges a pre-contract meeting with the consultant team and works contractors to discuss procedures that will be adopted during the construction stage.
There are a range of tasks necessary to prepare for the construction stage:
- The management contractor co-ordinates the issue of production information for construction.
- The client and management contractor prepare and agree schedules of conditions for adjacent properties or structures that will be retained.
- The client and management contractor check that all necessary insurance policies are in place for construction work and site ownership.
- The client and management contractor check that all necessary permissions, approvals, party wall agreements and other statutory requirements are in place and that all necessary planning conditions have been satisfied.
- If necessary, and if it has not already been done, the client appoints; party wall surveyor(s), an approved inspector, site inspectors and an in-house or outsourced engineering team to witness testing and commissioning and to take over the running of the services as soon as practical completion is certified.
- The works contractors each prepare detailed programmes for their works and issue these to the management contractor. The management contractor incorporates these into an overall project programme and short period programmes for the co-ordination of the works. In addition, the works contractors may be required to agree an outline programme with the client setting out dates for the provision of information required by the client's consultant team.The management contractor may wish to bring key dates to the attention of the client or consultant team, such as dates for decisions, dates for the release of information, or dates for works outside of the works contracts. The client should not approve any programmes as approval might be considered to relieve the management contractor of liability for programming the works in such a way as to achieve the completion date.
- The principal designer ensures that co-ordination procedures are in place for any design carried out by the works contractors.
- The client's contract administrator briefs site inspectors regarding procedures for inspecting and reporting on work on site as it progresses. This might include specific monitoring and reporting arrangements relating to the implementation of client policies such as environmental policies (on a large project this might involve the appointment of an environmental consultant specifically to perform that role).
- The client may need to put procedures in place to move some of its staff and equipment so that it can continue to operate effectively during construction.
- The management contractor agrees the basic principles with the design team to be used for grid lines and setting out of the site.
[edit] Mobilising.
Mobilisation may involve the management contractor carrying out the following tasks:
- Co-ordinating the preparation and issue of a project handbook setting out responsibilities, procedures, and lines of communication for the construction stage.
- Preparing method statements and obtaining method statements from works contractors.
- Preparing a site layout plan for construction.
- Making arrangements for site communications such as the receipt and distribution of post and information and communications technology (ICT).
- Managing specialist design and drawing approval. The management contractor may wish to appoint a design co-ordinator to be responsible for this.
- Advertising and selecting remaining contracts such as catering, security and cleaning contracts.
- Establishing a contract register scheduling: the contracts that have been placed, who signed them and when, what the value of the contract is and where it is stored. This can be crucial information if for example the management contractor becomes insolvent.
- Establishing an asset register scheduling what assets there are on site and who they belong to. This information may later be incorporated into the building owner's manual.
- Establishing all statutory site registers such as; lifting equipment, dangerous and explosive substance storage, scaffolding and accident reports etc.
- Complying with any statutory conditions that must be satisfied prior to construction commencing (such as tree protection, submission of contaminated soil disposal plans, approval of work adjacent to an operating rail track and so on).
- Ensuring (in their role as principal contractor) that workers are provided with suitable site induction, training and information to be able to work without undue risk to their health or safety.
- Establishing inspection regimes and quality assurance procedures for construction.
- Commissioning any further geotechnical survey work required.
- If it has not already been done, obtaining statutory utility drawings of all existing and surrounding services including details of any telecoms, wells and hydraulic mains.
- Arranging necessary road closures and restrictions, diversions of services and connections necessary for the works to be carried out.
- If it has not already been done, obtaining legal documentation describing precisely the site boundary and ownership.
- Preparing (in their role as principal contractor) a construction phase plan, if this has not already been done.
- Developing the site waste management plan (if required).
- Commissioning a survey team to establish semi-permanent setting-out theodolite base plates.
- If it has not already been done, arranging for the statutory utilities to provide the necessary water, power supplies, and telecom services required for construction activity.
- Notifying the local authority (or approved inspector) of their intention to begin construction.
- Informing the emergency services of their intention to begin construction.
- Notifying HSE if this has not already been done.
Featured articles and news
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.