Management contract: mobilisation
Mobilisation refers to the activities that should be carried out after the works contractors have been appointed, but before they commence work on site. It is a preparatory stage during which the majority of activities are managed by the management contractor.
[edit] Preparing for the construction stage.
The management contractor arranges a pre-contract meeting with the consultant team and works contractors to discuss procedures that will be adopted during the construction stage.
There are a range of tasks necessary to prepare for the construction stage:
- The management contractor co-ordinates the issue of production information for construction.
- The client and management contractor prepare and agree schedules of conditions for adjacent properties or structures that will be retained.
- The client and management contractor check that all necessary insurance policies are in place for construction work and site ownership.
- The client and management contractor check that all necessary permissions, approvals, party wall agreements and other statutory requirements are in place and that all necessary planning conditions have been satisfied.
- If necessary, and if it has not already been done, the client appoints; party wall surveyor(s), an approved inspector, site inspectors and an in-house or outsourced engineering team to witness testing and commissioning and to take over the running of the services as soon as practical completion is certified.
- The works contractors each prepare detailed programmes for their works and issue these to the management contractor. The management contractor incorporates these into an overall project programme and short period programmes for the co-ordination of the works. In addition, the works contractors may be required to agree an outline programme with the client setting out dates for the provision of information required by the client's consultant team.The management contractor may wish to bring key dates to the attention of the client or consultant team, such as dates for decisions, dates for the release of information, or dates for works outside of the works contracts. The client should not approve any programmes as approval might be considered to relieve the management contractor of liability for programming the works in such a way as to achieve the completion date.
- The principal designer ensures that co-ordination procedures are in place for any design carried out by the works contractors.
- The client's contract administrator briefs site inspectors regarding procedures for inspecting and reporting on work on site as it progresses. This might include specific monitoring and reporting arrangements relating to the implementation of client policies such as environmental policies (on a large project this might involve the appointment of an environmental consultant specifically to perform that role).
- The client may need to put procedures in place to move some of its staff and equipment so that it can continue to operate effectively during construction.
- The management contractor agrees the basic principles with the design team to be used for grid lines and setting out of the site.
[edit] Mobilising.
Mobilisation may involve the management contractor carrying out the following tasks:
- Co-ordinating the preparation and issue of a project handbook setting out responsibilities, procedures, and lines of communication for the construction stage.
- Preparing method statements and obtaining method statements from works contractors.
- Preparing a site layout plan for construction.
- Making arrangements for site communications such as the receipt and distribution of post and information and communications technology (ICT).
- Managing specialist design and drawing approval. The management contractor may wish to appoint a design co-ordinator to be responsible for this.
- Advertising and selecting remaining contracts such as catering, security and cleaning contracts.
- Establishing a contract register scheduling: the contracts that have been placed, who signed them and when, what the value of the contract is and where it is stored. This can be crucial information if for example the management contractor becomes insolvent.
- Establishing an asset register scheduling what assets there are on site and who they belong to. This information may later be incorporated into the building owner's manual.
- Establishing all statutory site registers such as; lifting equipment, dangerous and explosive substance storage, scaffolding and accident reports etc.
- Complying with any statutory conditions that must be satisfied prior to construction commencing (such as tree protection, submission of contaminated soil disposal plans, approval of work adjacent to an operating rail track and so on).
- Ensuring (in their role as principal contractor) that workers are provided with suitable site induction, training and information to be able to work without undue risk to their health or safety.
- Establishing inspection regimes and quality assurance procedures for construction.
- Commissioning any further geotechnical survey work required.
- If it has not already been done, obtaining statutory utility drawings of all existing and surrounding services including details of any telecoms, wells and hydraulic mains.
- Arranging necessary road closures and restrictions, diversions of services and connections necessary for the works to be carried out.
- If it has not already been done, obtaining legal documentation describing precisely the site boundary and ownership.
- Preparing (in their role as principal contractor) a construction phase plan, if this has not already been done.
- Developing the site waste management plan (if required).
- Commissioning a survey team to establish semi-permanent setting-out theodolite base plates.
- If it has not already been done, arranging for the statutory utilities to provide the necessary water, power supplies, and telecom services required for construction activity.
- Notifying the local authority (or approved inspector) of their intention to begin construction.
- Informing the emergency services of their intention to begin construction.
- Notifying HSE if this has not already been done.
Featured articles and news
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
A brief run down of changes intentions from April in an onwards.