Management contract: mobilisation
Mobilisation refers to the activities that should be carried out after the works contractors have been appointed, but before they commence work on site. It is a preparatory stage during which the majority of activities are managed by the management contractor.
[edit] Preparing for the construction stage.
The management contractor arranges a pre-contract meeting with the consultant team and works contractors to discuss procedures that will be adopted during the construction stage.
There are a range of tasks necessary to prepare for the construction stage:
- The management contractor co-ordinates the issue of production information for construction.
- The client and management contractor prepare and agree schedules of conditions for adjacent properties or structures that will be retained.
- The client and management contractor check that all necessary insurance policies are in place for construction work and site ownership.
- The client and management contractor check that all necessary permissions, approvals, party wall agreements and other statutory requirements are in place and that all necessary planning conditions have been satisfied.
- If necessary, and if it has not already been done, the client appoints; party wall surveyor(s), an approved inspector, site inspectors and an in-house or outsourced engineering team to witness testing and commissioning and to take over the running of the services as soon as practical completion is certified.
- The works contractors each prepare detailed programmes for their works and issue these to the management contractor. The management contractor incorporates these into an overall project programme and short period programmes for the co-ordination of the works. In addition, the works contractors may be required to agree an outline programme with the client setting out dates for the provision of information required by the client's consultant team.The management contractor may wish to bring key dates to the attention of the client or consultant team, such as dates for decisions, dates for the release of information, or dates for works outside of the works contracts. The client should not approve any programmes as approval might be considered to relieve the management contractor of liability for programming the works in such a way as to achieve the completion date.
- The principal designer ensures that co-ordination procedures are in place for any design carried out by the works contractors.
- The client's contract administrator briefs site inspectors regarding procedures for inspecting and reporting on work on site as it progresses. This might include specific monitoring and reporting arrangements relating to the implementation of client policies such as environmental policies (on a large project this might involve the appointment of an environmental consultant specifically to perform that role).
- The client may need to put procedures in place to move some of its staff and equipment so that it can continue to operate effectively during construction.
- The management contractor agrees the basic principles with the design team to be used for grid lines and setting out of the site.
[edit] Mobilising.
Mobilisation may involve the management contractor carrying out the following tasks:
- Co-ordinating the preparation and issue of a project handbook setting out responsibilities, procedures, and lines of communication for the construction stage.
- Preparing method statements and obtaining method statements from works contractors.
- Preparing a site layout plan for construction.
- Making arrangements for site communications such as the receipt and distribution of post and information and communications technology (ICT).
- Managing specialist design and drawing approval. The management contractor may wish to appoint a design co-ordinator to be responsible for this.
- Advertising and selecting remaining contracts such as catering, security and cleaning contracts.
- Establishing a contract register scheduling: the contracts that have been placed, who signed them and when, what the value of the contract is and where it is stored. This can be crucial information if for example the management contractor becomes insolvent.
- Establishing an asset register scheduling what assets there are on site and who they belong to. This information may later be incorporated into the building owner's manual.
- Establishing all statutory site registers such as; lifting equipment, dangerous and explosive substance storage, scaffolding and accident reports etc.
- Complying with any statutory conditions that must be satisfied prior to construction commencing (such as tree protection, submission of contaminated soil disposal plans, approval of work adjacent to an operating rail track and so on).
- Ensuring (in their role as principal contractor) that workers are provided with suitable site induction, training and information to be able to work without undue risk to their health or safety.
- Establishing inspection regimes and quality assurance procedures for construction.
- Commissioning any further geotechnical survey work required.
- If it has not already been done, obtaining statutory utility drawings of all existing and surrounding services including details of any telecoms, wells and hydraulic mains.
- Arranging necessary road closures and restrictions, diversions of services and connections necessary for the works to be carried out.
- If it has not already been done, obtaining legal documentation describing precisely the site boundary and ownership.
- Preparing (in their role as principal contractor) a construction phase plan, if this has not already been done.
- Developing the site waste management plan (if required).
- Commissioning a survey team to establish semi-permanent setting-out theodolite base plates.
- If it has not already been done, arranging for the statutory utilities to provide the necessary water, power supplies, and telecom services required for construction activity.
- Notifying the local authority (or approved inspector) of their intention to begin construction.
- Informing the emergency services of their intention to begin construction.
- Notifying HSE if this has not already been done.
Featured articles and news
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.