Pioneering cranage methodology
Powerhouse Parramatta has reached a new construction milestone with the first steel trusses on the project’s distinctive steel exoskeleton being installed by Marr’s cranes working on the project.
Powerhouse Parramatta is being constructed by Lendlease on behalf of the NSW Government. An architectural collaboration between Moreau Kusunoki (Lead Designer) and Genton (Local Architect), it is one of the largest structural engineering and architecturally complex projects underway in Australia. Marr has been engaged by Lendlease to provide the cranage solution.
On completion, Powerhouse Parramatta will be the largest museum in NSW at 30,000 square metres, featuring more than 18,000 square metres of exhibition and public space, including Australia’s largest column-free exhibition space. Designed so that its exterior superstructure is a celebrated architectural feature, the museum’s two buildings are designed with three types of steel lattices as an exoskeleton.
With the structural support for the trusses that achieve the column-free exhibition space sitting on the exterior of the building, the challenge from a construction point-of-view was how to install the heavy steel trusses and deliver the project to the architectural team’s vision. Knowing that an innovative cranage solution was needed, Lendlease engaged Marr during the planning stage.
Working in collaboration with Lendlease’s construction team before onsite works commenced, Marr’s solution was to install three of Marr’s Heavy Lift Luffing (HLL) tower cranes including a 330-tonne capacity Favelle Favco M2480D, 150-tonne capacity M1280D and 96-tonne capacity M860D.
By allowing bigger, heavier modularised sections of the exoskeleton including steel trusses weighing to be installed in a single lift, the cranage methodology will reduce the number of lifts required and decongest the site. With the first trusses installed weighing 50 tonnes, the heaviest lifts will be trusses weighing up to 120 tonnes.
According to Marr’s Design & Engineering Manager, Andrew Coffin, “From an engineering standpoint this project is a significant challenge due to its complexity. In partnering with Lendlease, as the managing contractor, we managed to jointly streamline the construction methodology and adopt a crane solution to tackle the complexity of the project and increase efficiency. The key was understanding the desired approach to building the project and designing the crane solution around that idea.”
“This is an incredibly exciting project to be part of. Just as Powerhouse Parramatta is a celebration of Australian innovation and achievement, its construction will be testimony to the impact that technology, innovation, design and engineering have on our world.,” said Marr’s Managing Director, Simon Marr.
“It took vision, innovation and collaboration to design a cranage solution that will deliver this amazing project, and Lendlease had the vision to see the benefits of what we could bring to this project. It’s a great example of achieving a better solution for the project team by asking ‘how do you want to build the project?’ and designing the cranage solution around a construction methodology instead of construction being driven by the limitations of the crane as we are constantly seeing in other parts of the world,” Mr Marr said.
With sustainability sitting at the heart of the building and its construction, Powerhouse Parramatta will be Parramatta’s first public 6 Star Green Star Building. It is also one of the first projects in Australia to use 100% renewable diesel (HVO100) in Marr’s cranes working on the project.
Construction of Powerhouse Parramatta is scheduled for completion in late 2024.
[edit] Related articles on Designing Buildings
- Amazing cranes.
- Avoiding crane collapses.
- Banksman.
- Bituminous mixing and laying plant.
- Cherry pickers.
- Compressed air plant.
- Concreting plant.
- Construction plant.
- Construction tools.
- Counterweights.
- Cranes.
- Crane supports.
- Crane regulations.
- Driving and riding safely for work.
- Earth-moving plant.
- Electromagnetic overhead cranes.
- Equipment in buildings.
- Excavating plant.
- Forklift truck.
- Gantry.
- Hoists.
- Lifting device.
- Pulley.
- Rubble chute.
- Scaffolding.
- Scissor lift.
- Site storage.
- Stacker.
- Temporary works.
- Types of crane.
- Winch.
- Work at height.
- Work at height regulations.
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.




















