What is a final account?
![]() |
In construction contracts, a final account is an agreed statement concerning the amount of money to be paid at the end of a building contract by the employer to the contractor. For more information see: Final account.
Contents |
Who prepares a final account?
Quantity surveyors generally prepare final accounts, in the manner that is best suited to the particular project, with the original contract sum as the starting point. Whilst the contract may give the employer the responsibility for preparing the final account, the best approach is generally for both the employer's quantity surveyor and the contractor’s quantity surveyor to work together to produce an agreed account.
Both the employer (or the employer’s representative) and the contractor sign the final account statement to signify that the final account figure represents the full and final settlement of all claims etc. The settlement of the final account will trigger a final account statement and ultimately, enable the contract administrator to issue the final certificate.
Objectives when preparing the final account include:
- Producing a clear statement showing the contract sum followed by all necessary adjustments to that sum.
- Complying with the terms and conditions of the relevant contract.
- All items fully assessed and adjustments made for variations, provisional sums, re-measured works etc.
- Work carried out on a day-works basis is included.
- Loss and expense claims / reimbursement accurately assessed and included.
- Fluctuations where applicable are included.
- Confirmation of the contractor’s agreement to the final account figure in writing.
Final account preparation guidelines
Under the terms and conditions of the contract, the contractor is generally required to provide the quantity surveyor with all documents necessary for the final account preparation not later than six months after practical completion. Within three months of receipt of these documents, the quantity surveyor is to prepare and ascertain the final account sum and send this to the contractor.
The bulk of the final account will generally consist of measured work priced at the original billed rates. If the contractor’s quantity surveyor has reason to doubt the accuracy of any of the original billed items, they can make a request to the quantity surveyor for that work to be measured on-site.
The adjustment of the contract sum in the final account normally falls under several relevant items, although the quantity surveyor must have regard to all the matters listed in the standard form of contract and conditions
The following are key items to be deducted:
- Prime-cost sums and amounts in respect of named subcontractors and associated contractor’s profit.
- Provisional sums and the value of work for which approximate quantities are included in contract bills.
- Variations that are omissions.
- Amounts allowable to the employer under the fluctuations clauses.
- Any other amount that is required by the contract to be deducted from the contract sum.
The following are key items to consider incorporating in the final account:
- The total amounts of nominated subcontractors finally adjusted in accordance with the relevant subcontract conditions.
- Where the contractor has tendered for work that was to have been performed by a nominated subcontractor and thier tender has been accepted, the amount of the tender suitably adjusted.
- Any amounts due to nominated suppliers, including cash discounts excluding VAT.
- The contractor’s profit on the above amounts.
- Any amounts payable by the employer relating to statutory fees and charges, opening up and testing, royalties and patent rights, and insurances.
- The value of work carried out against provisional sums or approximate quantities included in the contract bills.
- Any amounts payable by the employer to the contractor by way of reimbursement for direct loss/and or expense arising from matters materially affecting the regular progress of the works.
- Any amount expended by the contractor as a result of loss or damage by fire or other perils where the risks are insured by the employer and the contractor is entitled to reimbursement.
- Any amount payable to the contractor under the fluctuations clauses.
- Any other amount that is required by the contract to be added to the contract sum.
Conclusion
All relevant items must be shown separately in the final account, and the net amount of each variation and amounts due to each nominated subcontractor and nominated supplier listed. When preparing the final account, the employer's quantity surveyor should give the contractor’s quantity surveyor the opportunity to be present when measurements and details are taken or recorded, so that the document is prepared in full liaison with the contractor to avoid the possibility of disputes.
Delays in the settlement of the final account represent additional cost to the contractor and in the majority of cases the employer is anxious to know their ultimate financial commitment. The project manager and the quantity surveyor have a contractual responsibility under the contract to keep to the date stipulated in the contract for completion of the final account, and the contractor should give every assistance in the prompt provision of subcontractors' and suppliers' accounts, agreement of measurement and prices, and the supply of all necessary supporting data.
Related articles on Designing Buildings Wiki
- Accounting.
- Campaign for cash retentions reform.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plans.
- Cost reporting.
- Cost value reconciliation.
- Defects.
- Escrow.
- Final certificate.
- Fluctuations.
- Housing Grants, Construction and Regeneration Act.
- Liquidated damages.
- Loss and expense.
- New Rules of Measurement.
- Outturn cost.
- Pre-tender estimate.
- Prime cost sums.
- Provisional sums.
- Retention bond.
- Scott schedule.
- Tender pricing document
- Variations.
- Whole-life costs.
Featured articles and news
Grenfell Tower fire – eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.