Scaffolding
Scaffolding provides a temporary safe working platform for activities such as:
It is formed from individual tubes and joints or proprietary components.
There are two main types of scaffolding:
- Freestanding scaffolds, such as Independent towers,
- Independent tied scaffolds, such as independent towers tied to an adjacent structure.
NB For more types of scaffold, see Types of scaffolding.
The most common piece of structure used in scaffolding is the scaffold tube (known as a standard). The tube generally comes in two thicknesses, 3.2 mm or 4 mm. The tubes are galvanised due to their exposure to the elements and axial capacity loads are given either ‘as new’ or ‘used.’ Capacities of tubes used in tension are usually limited by the safe slip load capacity of the coupler, which is far lower than the actual tensile resistance of the tube.
Scaffolding is designed for its self-weight, i.e. the weight of the boards, tubes, guardrails, toeboards, etc. and imposed loads such as wind. The imposed load applied to the scaffolding depends on its use.
Four classes of loading are available:
- Service Class 1 - 0.75 kN/m2 – Inspection and very light duty access
- Service Class 2 - 1.50 kN/m2 – Light duty such as painting and cleaning
- Service Class 3 - 2.00 kN/m2 – General building work, brickwork, etc.
- Service Class 4 - 3.00 kN/m2 – Heavy duty such as masonry and heavy cladding
The wind load applied to scaffolding will change depending on whether sheeting or debris nets are used. The magnitude of the wind load will alter the required capacity of the ties and may affect their frequency.
When scaffolding is tied to a building it uses the permanent structure of the building to provide stability. The selection of tie positions should be tested and checked before use and the suitability of the permanent structures composition to carry the ties should be analysed.
Scaffolding is also braced laterally using façade and ledger bracing.
Workmanship and inspection is vital for the erection and dismantling of scaffolding and must be undertaken by competent personal under supervision.
For more information, see Scaffold register.
For information about removing scaffolding, see How to remove scaffolding.
The National Access and Scaffolding Confederation (NASC) has published TG20:21, which provides the definitive guidance for scaffolding constructed with tube and fittings throughout the UK. TG20 comprises four elements; the Operational Guide, the Design Guide, the User Guide and the NASC’s innovative, user-friendly and widely-adopted eGuide software.
Up until March 2021, this bundle came only in the form of three hard copy guides and a digital download, and was titled TG20:13. TG20:13 was formally withdrawn, in favour of fully adopting TG20:21, on October 12 2021. Further information can be found here.
Through TG20:21 the guides and eGuide are now available online, with the improved and expanded software and the associated and updated Operational and Design Guides accessible via the NASC ePortal.
The NASC has five membership categories; Contractor, Supplier, Design, Information and International Information.
[edit] Related articles on Designing Buildings
- Building wraps.
- CDM.
- Debris netting.
- Demolition.
- Facade retention.
- Falsework.
- Formwork.
- Gantry.
- How to remove scaffolding.
- How to use a ladder.
- Putlog holes.
- Roped access for conservation projects.
- Rubble chute.
- Scaffold register.
- Shoring.
- Temporary works.
- Ties.
- Trench support.
- Types of crane.
- Types of scaffolding.
- Work at height.
- Work at height checklist for managers.
- Work at height regulations.
- Working platform.
[edit] External references
- BS5975:2008 + A1: 2001 Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework (BSI 2011).
- The National Access And Scaffolding Confederation (NASC).
- Scaffolding Safety Tips
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.