Construction management
Construction management is a procurement route in which the works are constructed by a number of different trade contractors. These trade contractors are contracted to the client but managed by a construction manager (CM).
The employer places a direct contract with each of the trade contractors and utilises the expertise of a construction manager who acts as a consultant to coordinate the contracts. The trade contractors carry out the work and the construction manager supervises the construction process and coordinates the design team. The CM has no contractual links with the trade contractors or members of the design team. Their role includes preparation of the programme, determining requirements for site facilities, breaking down the project into suitable works packages, obtaining and evaluating tenders, co-ordinating and supervising the works.
Construction management differs from management contracting, in that management contractors place contracts with works contractors (equivalent to trade contractors in construction management) direct, whereas construction managers only manage the trade contracts, the contracts are placed by the client.
Construction management contracts might be used on large, complex projects were the advantages of CM can be put to use e.g. upfront buildability knowledge, programme advice, specialist input from trade contractors
- Where early start on site is key
- Flexibility in design, procurement, construction strategy
- Where price certainty before commencement is not key
- Where the client is experienced in construction
- What are the advantages?
- Overall project duration reduced by overlapping design and construction
- Construction manager can contribute to the design and project planning processes
- Roles, risks and relationships for all parties are clear
- Changes in design can be accommodated without paying a premium
- Prices may be lower due to direct contracts with trade contractors
- Client has means of redress to trade contractors through direct contractual links
- What are the disadvantages?
- Price certainty not achieved until last trade package is let
- Changes to later packages may adversely affect packages already let - expensive
- Need an informed, pro active client
- Client has a lot of consultants and contractors to deal with – not just one – more fees
Appointing a construction manager enables some trade packages to be tendered earlier than others, and sometimes, even before the design is completed. For example, piling might commence whilst the detailed design of above ground works continues. This can shorten the time taken to complete the project, however, it means that there will be price uncertainty until the design is complete and all contracts have been let.
The services provided by a construction manager might include:
- Advising on the development of the brief (if appointed at this stage).
- Advising on the procurement route.
- Advising on appointments (such as site inspectors).
- Advising on the feasibility, interfaces, buildability, cost and programming of the design.
- Advising on statutory approvals.
- Defining key performance indicators for trade contractors.
- Advising on the need for mock ups, samples, tests and inspections.
- Acting as the principal contractor.
- Cost planning and cost control.
- Preparing a construction programme and defining methods of working on site.
- Identifying potential trade contracts.
- Tendering trade contracts.
- Consenting to sub-contracting of work by trade contractors.
- Arranging for site accommodation, welfare facilities, fences, hoardings, roads and walkways, drainage, power and water supply.
- Co-ordinating setting out.
- Arranging labour for certain site activities (such as cleaning).
- Managing site inspectors.
- Co-ordinating the release of information.
- Managing and co-ordinating trade contracts, including acting as contract administrator, carrying out or co-ordinating inspections, issuing instructions and certificates, etc.
- Co-ordinating the work of statutory undertakers.
- Witnessing tests and co-ordinating commissioning.
- Collating as-built information, building owner's manual, building user's handbook, project handbook, health and safety file, pre-construction information and construction phase plan.
- Monitoring key performance indicators.
- Managing the site.
- Chairing site progress meetings and preparing progress reports for the client.
[edit] Related articles on Designing Buildings
- Bill of quantities.
- Construction management.
- Contract conditions.
- Contract sum.
- Defined provisional sum.
- Difference between preliminaries and preambles.
- Extension of time.
- Preliminaries.
- Prime cost sum.
- Procurement route.
- Provisional sum.
- The difference between a prime cost sum and a provisional sum.
- Undefined provisional sum.
- Variations.
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.