Last edited 06 Oct 2026

Measurement

Pencil-g6a300c298 1280.jpg

Contents

[edit] Introduction

Note: This article refers to the measurement of quantities for construction works. For articles about more general measurements, see the list of articles in the measurement category.

See also:

[edit] Measurement of quantities for construction works

The measurement of quantities for construction works involves the transformation of drawn information into descriptions and quantities. This process is undertaken to value, cost, and price construction work, as well as enabling effective management of the design and construction process. The measurement process is not restricted to the quantity surveyor producing a bill of quantities for contractors to price during tendering. It is also used in both pre- and post-contract work, helping assess the likely cost of the works, and determining what contractors and subcontractors should be paid for work that has been completed.

[edit] Pre-contract measurement

During the early design stages, the quantity surveyor (or cost consultant) will measure the dimensions of the building to produce budget estimates, perhaps based on benchmarking against similar buildings. As the design develops, they will measure more detailed approximate quantities for cost planning purposes, ensuring that the design can be achieved within the budget. The quantity surveyor then measures the completed working drawings to produce a bill of quantities. Contractors tender for the job by pricing the work described in the bill of quantities.

[edit] Post-contract measurement

The contractor may use measurement for:

The quantity surveyor may undertake measurement for:

[edit] Levels of detail required for measured information

The degree of detail to which construction work can be measured varies according to its use and the stage in the project. In the very early design stages, there is not much detail available, so estimates are based on general parameters, such as:

As the design progresses and more information is known, estimates can become more detailed, such as elemental estimates (for walls, floors, roof, frame, etc.).

During the later stages of the design, the work required to construct the building may be measured by:

NB: Bills of quantities are normally only prepared on larger projects. On smaller projects, or for alteration work the contractor may be expected to measure their own quantities from drawings and schedules of work. Schedules of work are 'without quantities' instructional lists that allow the contractor to identify significant work and materials that will be needed to complete the works and calculate the quantities that will be required.

For more information see: Bills of quantities.

[edit] Standard methods of measurement

It is important that there is a uniform basis for measuring building works for industry-wide consistency and to allow benchmarking, encourage the adoption of best practice and help avoid disputes.

A standard method of measurement:

The most commonly used standard method of measurement for building works is the New Rules of Measurement (NRM), which replaced the Standard Method of Measurement, seventh edition (SMM7). NRM2 was published in 2012 and formally replaced SMM7 on 1 July 2013. The New Rules of Measurement are published by the Royal Institution of Chartered Surveyors (RICS) and prepared by the Quantity Surveying and Construction Professional Group. NRM1, NRM2 and NRM3 were republished in new editions between October 2021 and October 2022, and have since been reissued, unchanged, as RICS professional practice information.

NRM provides a set of detailed measurement rules for the preparation of bills of quantities or schedules of rates for the purpose of obtaining a tender price. It also deals with the quantification of non-measurable work items, contractor designed works and risks. Guidance is also provided on the content, structure and format of bills of quantities, as well as the benefits and uses of bills of quantities.

For more information see: New Rules of Measurement.

[edit] How measurement is done

[edit] What is taking off?

The term 'taking off' refers to the process of identifying elements of construction works that can be measured and priced. Those elements can be measured in number, length, area, volume, weight or time, then collated and structured to produce an unpriced bill of quantities. This process is sometimes referred to as 'working up'.

For more information see: Taking off.

See also: How to take off construction works.

[edit] What are the standard measurement conventions?

Always measure gross building area and then deduct items such as exterior walls to find floor space area. Always measure on the centre line of the material.

[edit] Calculating girths and centre lines

The centre line is half way between the external girth and the internal girth.

Measurement1.png

Centre line (CL) = (Internal girth + external girth)/2

CL = Internal girth + (No. of corners) x 2(wall width)/2

or

CL = External girth - (No. of corners) x 2(wall width)/2

[edit] Calculating girths for irregular shaped buildings

Measurement2.png

EXTERNAL GIRTH INTERNAL GIRTH
2.00 1.50
1.00 1.00
1.00 1.00
1.00 0.50
3.00 2.50
2.00 1.50
Total = 10.00 Total = 8.00

CL = Internal girth + (No. of corners) x 2(wall width)/2

Number of external corners = 5

Number of internal corners = 1

External corners - Internal corner = 4

This occurs regardless of shape providing the walls encompass 360°.

In the example above, the internal girth was 8.00, and the external girth was 10.00.

Difference = 2.00 m = 4 x 2(wall width)/2

[edit] Buildings with an inset

Measurement3.png

Girth = 2(length + width) + 2(depth of inset)

= 2(6.00 + 5.00) + 2(2.60)

= 27.20 m

[edit] Important centre lines used for measuring foundations

Measurement4.png

[edit] Building information modelling (BIM) and measurement

Increasingly, software packages are available to assist in the preparation of bills of quantities, and building information modelling systems can be used to produce bills of quantities from information already contained within the model.

For more information see: Building information modelling.

[edit] Related articles on Designing Buildings

[edit] External references

Comments

To make a comment about this article, click 'Add a comment' above.

Separate your comments from any existing comments by inserting a horizontal line.


Really helpful article, but it would be useful to have more detail about the practicalities of how it is done.

thanks


Designing Buildings Anywhere

Get the Firefox add-on to access 20,000 definitions direct from any website

Find out more Accept cookies and
don't show me this again