Taking off construction works
The term ‘taking off’ refers to the process of identifying elements of construction works that can be measured and priced. This is necessary to produce bills of quantities and requires that the design is complete and a specification has been prepared.
Analysis of drawings and specifications allows the cost consultant (usually a quantity surveyor) to prepare a taking off list, which lists all of the individual elements that comprise the works.
These elements can then be measured in number, length, area, volume, weight or time then collated and structured to produce an unpriced bill of quantities. This process is sometimes referred to as ‘working up’.
Where there may be uncertainty about some elements, they may be entered onto a query sheet that can be issued to the appropriate members of the consultant team for clarification.
The unpriced bill of quantities will have price and rate columns for tenderers to complete.
The bill of quantities is issued to tenderers for them to prepare a price for carrying out the works. The bill of quantities assists tenderers in the calculation of construction costs for their tender, and, as it means all tendering contractors will be pricing the same quantities (rather than taking off quantities from the drawings and specifications themselves), it also provides a fair and accurate system for tendering.
Best practice for the preparation of bills of quantities is set out in the New Rules of Measurement (NRM) published by the Royal Institute of Chartered Surveyors and replacing Standard Method of Measurement, seventh edition (SMM7). Adopting the New Rules of Measurement means that all projects are taken off in the same way and in the same order following consistent rules.
Increasingly, software packages are available to assist in the preparation of preparation of bills of quantities, and building information modelling systems can be used to produce bills of quantities from information already contained within the model. The process in Building Information Modelling (BIM) is often referred to as material or quantity takeoff, which uses the underlying 3D parametric model to calculate materials takeoff for cost estimation, as well as in some cases embodied carbon calculations by adding the density factor and CO2 e per kg or volume of material.
In this process care must be taken that digital models are a fair representation of the actual product or component, for examples metal window frames being modelled as hollow extrusions rather than solid elements, the later can impact the material take-off dramatically increasing for example the assumed aluminium used by weight.
Bills of quantities are normally only prepared on larger projects. On smaller projects, or for alteration work, the contractor can be expected to measure their own quantities from drawings and schedules of work. Schedules of work are 'without quantities' instructional lists that allow the contractor to identify significant work and materials that will be needed to complete the works and to calculate the quantities that will be required.
For more information, see How to take off construction works.
[edit] Related articles on Designing Buildings
- Approximate bill of quantities.
- Approximate quantities cost plan.
- Bill of quantities.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Computers in tendering.
- Construction work packaging.
- Contract documents
- Cost plans.
- Elemental cost plan.
- Extra over (EO).
- How to take off construction works.
- Measured quantity.
- New Rules of Measurement.
- Spot items.
- Standard Method of Measurement (SMM7).
- Tender.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Working up construction works.
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
There is a detailed description of the traditional paper-based technique here: https://www.designingbuildings.co.uk/wiki/How_to_take_off_construction_works