How to take off construction works
Contents |
[edit] What is taking off?
The term ‘taking off’ or 'take off' or 'takeoff' refers to the process of identifying and quantifying elements of construction works that can be measured and priced. This can be used to produce bills of quantities that can be issued to tenderers for them to prepare a price for carrying out the works. Contractors and subcontractors may also use the process to determine quantities required if these have not been provided to them.
Taking off requires that the design is complete and a specification has been prepared.
For more information see: Taking off construction works.
Taking off can carried out using paper-based techniques, but it is now more commonly done on spreadsheets or using specialist software. The introduction of building information modelling has allowed the automation of some tasks associated with taking off. Whatever the process adopted, the underlying mathematics remain the same as for the traditional paper-based technique as described below.
[edit] Paper-based taking off
Traditional taking off used dimension paper which is made of a series of columns:
- The timesing column, which gives the factor of multiplication for the measurements in the dimension column.
- The dimension column, where the measurements are set down as taken from the drawings.
- The squaring column, where the calculated volumes, areas, and so on, are set out.
- The description column, where the description of the work item in relation to the measurements is written.
[edit] Dimensions for taking off
The dimensions that are measured will be in one of the following forms:
- Cubic measurements (e.g. 3 m x 3 m x 3 m).
- Square measurements (e.g. 3 m x 3 m), also known as superficial measurements.
- Linear measurements (e.g. 3 m).
- Enumerated items (e.g. ‘Nr. 3’).
- Item (e.g. ‘Testing’).
Dimensions are usually set down in order of horizontal length, horizontal width or breadth, and vertical depth or height. It is important for the sake of consistency throughout the taking off that this order is maintained.
[edit] Timesing for taking off
This is a method in which several items that have the same measurements can be set down without having to replicate calculations multiple times.
The number of times that the measurement in the dimension column is to be multiplied is set down in the timesing column and separated using a diagonal stroke. The same item can be timesed multiple times by setting down additional numbers in the timesing column.
In the first example below, the cubic measurement 3.00 x 2.00 x 1.00 is to be multiplied by 2.
In the second example below, the same measurement, once multiplied by 2, is then multiplied by 4.
[edit] Dotting on
Dotting on is used to add dimensions together in the timesing column rather than multiplying. The numbers are positioned diagonally in the column with the dot between them to avoid any confusion with decimals.
In the first example below, the cubic measurement 3.00 x 2.00 x 1.00 is multiplied by (1 + 4) 5.
In the second example below, the same measurement is multiplied by (1 + 4) 5, which is then multiplied by 2.
[edit] Waste calculations
It is important that any calculations done to work out the dimensions that are entered into the dimension column are written down as waste calculations on the right-hand side of the description column. This is so that if someone reviews the taking off to check for accuracy, the process by which the final figures have been calculated can be traced back.
[edit] Alterations
Where incorrect dimensions have been set down, they should be neatly crossed out with ‘nil’ written alongside in the squaring column. This indicates that the dimensions are cancelled. Care should be taken to avoid confusion with the ‘nil’ label in terms of how many figures are to be cancelled and which are still to be used in the calculations.
In the example below, the square measurement 4.00 x 2.00 has been cancelled.
[edit] Descriptions
The description of the item being measured is included in the description column alongside the calculations. The contents of the description should correspond to the New Rules of Measurement (NRM). Where there are more than one set of calculations associated with the same description, then they can be bracketed together on the outside of the squaring column.
[edit] Anding-on
This is where there are two or more descriptions that apply to the same measurement. The descriptions are separated in the description column by ‘&’ so as to clearly distinguish between them. They can also be bracketed together for clarity.
Where items are to be deducted or added, they are preceded by ‘Deduct’ or ‘Add’ in the description column.
[edit] Related articles on Designing Buildings
- Advantages of a bill of quantities.
- Area.
- Bill of quantities.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Computers in tendering.
- Conversion of material volumes.
- Elemental cost plan.
- Extra over (EO).
- Firm bill of quantities.
- Measurement.
- Measurement of existing buildings.
- New Rules of Measurement.
- NRM 1.
- NRM 2.
- Quantity surveyor.
- Size.
- Spot items.
- Taking off construction works.
- Tender.
- Working up construction works.
[edit] External references
- ‘Willis’s Elements of Quantity Surveying’ (10th ed.), LEE, S., TRENCH, W., WILLIS, A., Blackwell Publishing (2005)
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
This artical is very useful for me for my studies.