A major lift on Brisbane's Kangaroo Point Bridge
Kangaroo Point Bridge has reached a new construction milestone with the final piece of the 95-metre-tall mast centrepiece installed by Marr Contracting’s M2480D tower crane working on the project.
Located on Brisbane’s busy river, the key challenge for the project was how to construct the bridge mast while minimising potential impacts on the public ferries and private vessels that use the Brisbane River daily.
The BESIX Watpac-led consortium, Connect Brisbane, who is delivering the project on behalf of Brisbane City Council, engaged Marr early in the design phase to develop a lifting strategy that supported their preferred construction methodology and addressed the challenges of constructing the 95-metre-tall mast.
According to BESIX Watpac Project Director, Rowan Riggall, “Our in-house engineering team was instrumental in identifying this crane at tender phase as the preferred lifting solution for the project. After comparing barge crane and tower crane options, the team confirmed the M2480D was the most suitable crane in the Australian market capable of lifting the fully assembled mast head.”
Working with Marr’s Brisbane-based engineers, Robert Bird Group, Marr developed a solution using an M2480D Heavy Lift Luffing (HLL) tower crane with a 64-metre-long boom installed on a platform in the middle of Brisbane River.
This configuration allowed the 25-metre-tall pre-fabricated steel masthead weighing 180 tonnes to be lifted to a height of 95 metres – a feat that wouldn’t have been possible using a more traditional approach of crawler cranes.
The lift was the heaviest to be undertaken as part of Marr’s scope of work including more than 10 major lifts and general construction lifting requirements over a period of 12 months.
“Reaping the benefits of modularised construction with fewer, heavier lifts is not only helping to deliver a safer, more productive site; but also allowing our client to share the economic benefit delivered by the project by engaging more South East Queensland businesses away from the workfront,” said Marr’s Managing Director, Simon Marr.
[edit] ABOUT KANGAROO POINT BRIDGE
An initiative by Brisbane City Council, the Kangaroo Point Bridge will be an iconic landmark destination connecting Brisbane’s CBD and eastern suburbs.
At a length of 460 metres, the bridge will be among the longest span cable stay pedestrian and cycle bridges in the world and a must-visit destination in Brisbane.
In June 2021, Brisbane City Council awarded the contract to design and construct the Bridge to the Connect Brisbane, following a detailed procurement process.
Led by BESIX Watpac, the Connect Brisbane consortium consists of bridge design, engineering and construction specialists including Rizzani de Eccher, WSP, Dissing + Weitling, Blight Rayner, Aspect Studios, Right Angle Studios and Rowland.
Construction of the Kangaroo Point Bridge is anticipated to be completed in 2024.
[edit] Related articles on Designing Buildings
- Amazing cranes.
- Avoiding crane collapses.
- Banksman.
- Bituminous mixing and laying plant.
- Cherry pickers.
- Compressed air plant.
- Concreting plant.
- Construction plant.
- Construction tools.
- Counterweights.
- Cranes.
- Crane supports.
- Crane regulations.
- Driving and riding safely for work.
- Earth-moving plant.
- Electromagnetic overhead cranes.
- Equipment in buildings.
- Excavating plant.
- Forklift truck.
- Gantry.
- Hoists.
- Lifting device.
- Pulley.
- Rubble chute.
- Scaffolding.
- Scissor lift.
- Site storage.
- Stacker.
- Temporary works.
- Types of crane.
- Winch.
- Work at height.
- Work at height regulations.
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).