Allowances in construction
The term allowance might generally be defined as an amount of something that is allowed or permitted, often within rules, regulations or contractual agreements, commonly in relation money but not exclusively. Allowances can also be used in relation to time, distances, volumes, risks and benefits. Below are some examples of allowances that might be found in relation to the construction of buildings.
In a construction contract allowances are often used to mean budgets that are established for specific scopes of the work that cannot be clearly defined at the time of bid, but that are set at a maximum estimate not to be exceed. A provisional sum is a type of allowance (or best guess), usually estimated by a cost consultant, that is inserted into tender documents for a specific element of the works that is not yet defined in enough detail for tenderers to accurately price.
Time Risk Allowance (TRA) is the amount of time allowed by a contractor in programming activities to allow for the risk of delay should problems arise, such as poor weather and inefficiencies on site that have a reasonable probability of occurring but are not significant enough to merit inclusion in the risk register. It is a term used in the NEC along with 'float’ (Total and terminal floats) being the time an activity can be delayed from its early start date without delaying the planned completion date.
Risk allowance according to NRM1 (Order of cost estimating and cost planning for capital building work) the term 'risk allowance' refers to 'the amount aded to the base cost estimate for items that cannot be precisely predicted to arrive at the cost limit'. According to the International Cost Management Standard (Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions, 2021), risk allowance is 'a quantitative allowance set aside as a precaution against risks and future needs to allow for the uncertainty of outcome. This may include an allowance for optimism bias and a contingency sum’ (Contingency allowance).
Fitting allowance in plumbing terms is the extra part of pipe connections minus the thread engagement (the section of pipe where the male and female elements cross) For example in an elbow joint, the fitting allowance is likely to be the outermost bend in the elbow (minus the two sections design to receive and over lap with the new pipe fitting).
Machining allowance is a layer of oversized material calculated on a raw product prior to final machining which will be removed during the final machining of the product.
Corrosion allowance is a layer of oversized material calculated on a product to allow for any corrosion likely to occur over its longer use to allow it to still function. For example oversized links of a metal chain to allow for future corrosion.
Pattern allowances are used to describe over sized moulds to account for shrinkage that is likely to occur from each casting.
Capital allowances are a group of UK income tax and corporation tax reliefs that are available to businesses for capital expenditure. The Enhanced Capital Allowance (ECA) scheme more specifically was a scheme that allowed businesses to write off the entire cost of any product included on the Energy Technology List (ETL) against taxable profits, in 2018 it was announced that the ECA and First Year Tax Credits Scheme (FYTC) would end from April 2020 for products on the ETL which was updated to remove references to the ECA.
Business premises renovation allowance (BPRA) was a temporary 100% capital allowance on expenditure incurred on or in connection with the conversion, renovation or repair of business premises, introduced in the Capital Allowances Act 2001. It was intended to encourage investment in derelict or unused properties in disadvantaged areas in order to bring them back into use, it was subsequently withdrawn in 2017.
Industrial Buildings Allowance (IBA) was introduced between 1945 and 2008, they were withdrawn in 2011. It was part of the Income Tax Act to boost post-war productivity in industry, giving a tax relief on the capital cost of constructing or purchasing a manufacturing or processing building. It was also broadened to include allowances on infrastructure such as tunnels, bridges, roads used for highway concessions, qualifying hotels and commercial buildings in enterprise zones.
Residual uncertainty allowance according to the Culvert, screen and outfall manual, (CIRIA C786) is ‘An allowance added on to design water level for uncertainty in hydrology and hydraulic assessment.’ whilst Freeboard allowance covers uncertainty for any other physical processes.
Domestic load connection allowance according to The Energy White Paper, Powering our Net Zero Future (CP 337) by HM Government (2020) is ‘the duty that network owners have to provide the first 10 metres of a gas connection free of charge to customers.’
Local housing allowance according to RICS Valuation of land for affordable housing (2016) ‘is housing benefit available to low income households.'
[edit] Related articles on Designing Buildings
- Business premises renovation allowance.
- Capital allowance.
- Domestic load connection allowance.
- Enhanced Capital Allowance scheme.
- Industrial Buildings Allowance (IBA).
- Local housing allowance.
- Preliminary business case for construction project.
- Risk allowance.
- Residual uncertainty allowance.
- Time Risk Allowance TRA.
Featured articles and news
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.