New Rules of Measurement
For a comparison of the Standard Method of Measurement and the New Rules of Measurement see: Comparison of SMM7 with NRM2.
[edit] Introduction
The New Rules of Measurement (NRM) are published by the Royal Institution of Chartered Surveyors' (RICS) Quantity Surveying and Construction Professional Group. They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects. Adopting a standard methodology such as NRM facilitates consistency and benchmarking and helps avoid disputes.
NRM is a suite of documents, comprising three volumes; NRM1, NRM2 and NRM3.
[edit] NRM1: Order of cost estimating and cost planning for capital building works.
NRM 1 was first published in February 2009 (as NRM Order of cost estimating and elemental cost planning). Now in its second edition, it provides guidance on the quantification of building works in order to prepare order of cost estimates and cost plans, as well as approximate estimates. It also includes guidance about quantifying wider costs such as preliminaries, overheads and profit, risk allowances, and inflation.
The second edition has been renamed to better distinguish between capital building works and building maintenance works, and the arrangement of elements has been revised. It became operative on 1 January 2013.
See NRM1 for more information.
[edit] NRM2: Detailed measurement for building works.
NRM2 was published in April 2012. It became operative on 1 January 2013 and replaced the Standard Method of Measurement, seventh edition (SMM7) on 1 July 2013.
NRM2 establishes detailed measurement rules allowing the preparation of bills of quantities, quantified schedules of works and schedules of rates in order to obtain tender prices. Guidance is also provided on the content, structure and format of bills of quantities.
See NRM2 for more information.
[edit] NRM3 - Order of cost estimating and cost planning for building maintenance works.
NRM3 was published in March 2014. It allows the quantification and description of maintenance works. It can be used for initial order of cost estimates, general cost plans and asset-specific cost plans. It also provides guidance on procurement and cost control.
NRM3 also offers guidance about the measurement of other items associated with maintenance works that are not included in work items.
See NRM3 for more information.
[edit] Reasons for the changes
It is suggested by the RICS that together, the new suite of documents will better reflect the way the industry works, for example:
- Better meeting the needs of clients.
- Providing for more up-front detail.
- Allowing better consideration of the full costs of a construction project (for example, marketing costs, fees and charges, the cost of acquiring land, planning costs, relocation costs, the cost of finance and so on).
- Providing a better method for quantifying risk.
The RICS also suggest that it will facilitate “...greater cross-industry working, the introduction of Building Information Modelling and effectively analysing the costs of construction projects” ref RICS.
As well as a set of rules for how to quantify building work, NRM is intended to provide a toolkit for cost management that will be central to controlling costs as a project develops. It provides guidance on how measurement changes as design progresses, how cost centres can be included in a single project cost plan, how to assess the cost of risk, how to assess fees, what information is required to make key decisions and so on.
The new NRM volumes were published alongside guidance on conflict avoidance and dispute resolution and retention. These will form part of the RICS QS and construction standards (the Black Book).
Notes:
- Contracts that refer to SMM7 will have to be revised when it is superceded by NRM. Many of the publishing bodies are now preparing amendments (for example JCT).
- NRM has moved away from the Common Arrangement of Work Sections (CAWS) to adopt its own system of indexing.
- For a detailed comparison of NRM2 with SMM7, see Comparison of SMM7 with NRM2.
- The New Rules of Measurement are accompanied by the 'Black Book', the QS and construction standards. Together they provide a suite of tools to help the construction industry work more collaboratively and consistently.
[edit] Related articles on Designing Buildings
- All-in rates.
- Approximate quantities.
- BCIS.
- BCIS elements.
- Bill of quantities.
- Black book.
- Building People.
- Classification, an introduction.
- Code of measuring practice.
- Common Arrangement of Work Sections (CAWS).
- Comparison of SMM7 with NRM2.
- Conversion of material volumes.
- Cost plans.
- Elemental cost plan.
- Measurement.
- NRM1.
- NRM2.
- NRM3.
- Order of cost estimate.
- RICS.
- RICS Property Measurement.
- RICS publishes Land Measurement for Planning and Development Purposes.
- Schedule of work.
- Spon's Price Book.
- Standard Method of Measurement (SMM7).
- Surveyor.
- Tender.
- Tender documentation.
- Uniclass.
[edit] External references
- RICS: RICS has released new guidance for quantity surveyors and other members working in the construction sector.
- RICS: NRM 1 and NRM 2 are available.
- nbs video: The New Rules of Measurement.
- RICS QS and construction standards (the Black Book).
- nbs: Coordinating Common Arrangment, Uniclass, NBS and Rules of Measurement.
Featured articles and news
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
Comments
the 3 volumes of NRM were updated in Dec 2021.