Traditional contract: mobilisation

Project plan traditional contract.jpg

Mobilisation refers to the activities carried out after the client has selected the main contractor, but before the contractor commences work on site. It is a preparatory stage during which the majority of activities are managed by the contractor.

[edit] Preparing for the construction stage.

The contract administrator arranges a pre-contract meeting to discuss procedures that will be adopted during the construction stage.

There are a range of tasks necessary to prepare for the construction stage:

[edit] Mobilising the contractor.

Mobilisation may involve the contractor carrying out the following tasks: