Traditional contract: construction
During this stage the contractor takes possession of the site to carry out the works. When the works are complete, the certificate of practical completion is issued and the site is handed back to the client.
Contents |
[edit] Starting the work stage.
The contract administrator arranges a handover meeting for the contractor to take possession of the site. See article handover to contractor.
Before work on site proceeds the principal contractor and the client confirm that suitable welfare facilities have been provided and that a suitable construction phase plan has been prepared.
[edit] Construction.
The lead designer co-ordinates the preparation and issue of any additional information required by the contractor and co-ordinates the review of design information prepared by the contractor.
Where there are any proposed variations, procedures for their valuation should be implemented (as described in the contract). Where variations exceed the delegated authority of the contract administrator, approval should be requested from the client.
The contract administrator co-ordinates site inspections and issues instructions as required and assesses any claims for extension of time or loss and expense with advice from the cost consultant and designers.
The cost consultant prepares regular valuation statements for interim payments (as set out in the contract). The contract administrator checks the preparation of the valuation statements and issues interim certificates (payment notices). The notices must be issued within five days of the dates for payment set out in the contract. If the client intends to pay a different amount from that shown on an interim certificate, then they must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The client makes payments to the contractor by the final date for payment.
The contract administrator holds regular construction progress meetings attended by the contractor and members of the consultant team if necessary. The contractor and cost consultant (and sometimes the consultant team) submit progress reports to the contract administrator during these meetings, and then the contract administrator prepares construction progress reports for the client.
[edit] Preparing for occupation.
The client begins preparations for occupation of the development, including the preparation of an operational policy and migration strategy setting out how they will manage the transition into and the operation of the new facility.
The client may have an 'occupation services contract' for delivering and installing equipment, fixtures and furniture (sometimes from other premises). This contract may also pick up small building changes that they consider would be too costly to be instructed under the main contract.
The client should ensure they have sufficient funds to release 50% of the retention upon certification of practical completion.
[edit] Inspections, commissioning and testing.
The lead consultant and client (generally representatives of the facilities management department) agree procedures for inspections, commissioning, testing and client training with the contractor.
If it has not already been done, the client appoints an in-house or outsourced engineering team to witness testing and commissioning and to take over the running of the services as soon as practical completion is certified.
The services engineer co-ordinates procedures for inspections, commissioning, testing and client training in relation to building services. The lead designer co-ordinates procedures for inspections, commissioning, testing and client training in relation to other aspects of the building.
The contractor rectifies any defects that become apparent during commissioning, testing and inspection procedures.
[edit] Practical completion.
The contractor prepares a draft building owner's manual and if required a building user's guide. The principal designer completes the health and safety file and the lead designer co-ordinates the preparation of the building log book.
The contractor confirms to the contract administrator that the works are complete
The contractor arranges for final inspection of the works by the building control inspector (or approved inspector) and arranges for the issue of a building regulations completion certificate. NB Within 5 days of the completion of the building, the contractor must notify building control that the works have been carried out in accordance with the specification submitted with the building emission rate (BER) calculations, or the changes that have been made (see emission rates for more information)
The contract administrator arranges a handover meeting to handover the site to the client (see article handover to client).
The cost consultant prepares a valuation statement. The contract administrator checks the preparation of the valuation statement and issues the issues the certificate of practical completion and interim certificate (payment notice). If the client intends to pay a different amount from that shown on the interim certificate, then they must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The client makes payment to the contractor by the final date for payment (this will include release of 50% of the retention)
The contract administrator prepares and submits a construction stage report for the client. The client assesses the construction stage report, and gives instructions as necessary.
Featured articles and news
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.