Traditional contract: occupation and defects liability period
The occupation and defects liability period takes place after the client has taken possession of the development for occupation. During this stage, any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed. As the development is now occupied, and the contractor no longer has possession of the site, close co-operation is required between the contractor and the client so as so not to disturb occupants, whose activities will take priority over work required to rectify defects.
[edit] Rectifying defects.
The contract administrator arranges a start-up meeting to plan the work stage.
If the contract allows, the contract administrator may review all relevant events that might be considered to have affected the completion date and may adjust the completion date accordingly.
The client reports any defects in the works to the contract administrator. On large projects the contractor may set up a hot desk for responding to any complaints or to provide assistance required by the incoming occupants. The contract administrator, takes advice from the consultant team and instructs the contractor to rectify the defects. The contractor and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary for the client to re-appoint the principal designer (whose appointment may have terminated on certification of practical completion) and it may be necessary to amend the health and safety file.
If any amounts are due to the contractor, the cost consultant prepares valuation statements for interim certificates. The contract administrator checks the preparation of the valuation statements and issues interim certificates (payment notices). The notices must be issued within five days of the dates for payment set out in the contract. If the client intends to pay a different amount from that shown on an interim certificate, then they must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The client makes payments to the contractor by the final date for payment.
At the end of the defects liability period, the contract administrator arranges inspections of the works and prepares a schedule of defects which is issued to the contractor. The contract administrator agrees the programme for rectification of items on the schedule of defects with the client and contractor, which should in any event be rectified within a reasonable time.
The contractor completes the building owner's manual, rectifies items listed on the schedules of defects and informs the contract administrator. The contract administrator arranges final inspections of the works and if satisfied issues the certificate of making good defects.
If a site waste management plan has been prepared, the contractor may reconcile the planned handling of waste (as described in the site waste management plan) against what actually happened and provide an explanation of any differences.
The contract administrator co-ordinates preparation of a final report and issues this to the client.
The cost consultant prepares the final account in consultation with the contractor and issues it to the contract administrator. The contract administrator checks the preparation of the final account and issues the final certificate (payment notice) this will include the release of any remaining retention. If the client intends to pay a different amount from that shown on the certificate, then they must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The client makes payment to the contractor by the final date for payment.
Issuing the final certificate will normally signify the end of the consultant teams appointments. If post-occupancy evaluation services are required, these may involve a new appointment.
Featured articles and news
AI and the challenges to intellectual property
The legal landscape of adopting AI now and in the future.
Worrying landscape for Welsh construction SMEs revealed.
In recent risk factor analysis report completed by CIOB.
Construction Sport survey highlights risks of dehydration
Supporting construction workers to avoid dangers.
Can your business afford to ignore mental well-being?
£70 - 100 billion annually in UK construction sector.
Mental health in the construction industry
World Mental Health Day 10 October.
Construction awards provide relief in wake of ISG collapse
Spike in major infrastructure awards, housing up but short of targets, are ISG collapse impacts yet to come.
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.
Renovating Union Chain Bridge.
AI tools for planning, design, construction and management
A long, continually expanding list, any more to add?