Traditional contract: post occupancy evaluation
Post occupancy evaluation is the process determining how successful the delivery of the project was, how successful the completed development is, where there is potential for further improvement, and what lessons can be learned for future projects. It can be particularly valuable to repeat developers and may be a requirement of some funding bodies.
In practice, post occupancy evaluation may begin during the defects liability period, and ideally the client should commit to carrying out post occupancy evaluation at the beginning of the project so that appointments and briefing documents can include a requirement to test whether objectives were achieved.
[edit] Appointing consultants.
Post occupancy evaluations may be carried out by an in-house team, by members of the consultant team or independent client advisers (we attribute them below to a consultant for simplicity of presentation). However, as post occupancy evaluation is likely to take place after the main construction contract has been completed, consultant team appointments may also be completed unless post occupation services were a specific requirement of the original appointments. If such services were not a requirement of the original appointments then new appointments may be necessary.
[edit] Carrying out a post project review.
A post project review may commence during the defects liability period. Its purpose is to evaluate the project delivery process rather than to assess performance in use (which is assessed later in this stage)
The consultant and client hold a start-up meeting to confirm the scope of evaluation required and agree the reporting procedures and programme for the stage. The client issues relevant information that may have been compiled during the design and construction phases to the consultant.
The consultant makes site visits to identify any issues that need to be addressed immediately. They may establish a help-desk and rapid response team if this has not already been done by the client.
The consultant monitors completion of the building owner's manual if this has not already been completed and ensures that other project documentation has been properly completed and handed over to the client (see handover to the client).
The consultant obtains the views of contractors, designers, suppliers and the client about how well the project was managed. This may include assessments of: the quality of briefing documents; the effectiveness of communications; the performance of the entire project team; quality issues; health and safety issues; certification; variations; claims disputes; and collaborative practices.
The consultant considers how well the delivery of the project performed against key performance indicators and evaluates what lessons can be learned from the approach taken. They then prepare an assessment and lessons learned report for the client.
[edit] Assessing performance in use.
Performance in use assessments cannot begin until 6 to 12 months after occupation, as operations may not be properly established and the building will not have operated in all seasons. It may then be part of a continuous process.
The consultant and client hold a start-up meeting to confirm the scope of the evaluation required and agree the reporting procedures and programme for the assessment. The client issues relevant information that may have been compiled to the consultant.
The consultant carries out evaluations of business objectives, which may include:
- The achievement of business case objectives.
- Whole-life costs and benefits against those forecast (including assessment of capital vs running costs).
- Whether the project continues to comply with the business strategy.
- Whether operations have improved.
- The resilience of the development and business to change.
- Business and user satisfaction (including staff and user retention and motivation).
The consultant carries out evaluations of the design, which may include:
- The effectiveness of the space planning.
- Aesthetic quality.
- The standards of lighting, acoustic environment, ventilation, temperature and humidity.
- Air-pollution and air quality.
- User comfort.
- Maintenance and occupancy costs.
- Defects.
- The balance between capital and running costs.
- An assessment of whether the development is being operated as designed.
- Environmental performance and energy consumption in use.
The consultant prepares a report that:
- Compares their findings to the original targets set out in business case (the original targets may need to be updated to reflect changes to the project brief during the design process, inflation etc).
- Compares findings to other projects and industry standards.
- Compares the outcome of the project with the position had the project not taken place.
- Identifies issues and recommends remedies.
- Makes recommendations for improvements in performance for future projects.
Other services that could be provided by consultants during this period might include: providing advice on letting, rating, maintenance, energy consumption, insurance, tenants queries, facilities management, the production of energy performance certificates, BREEAM assessments, the preparation of tender documents for maintenance and operation contracts and so on.
Featured articles and news
Celebrating architecture's eloquent champions.
Unusual perspectives on 1960s’ thinking.
AI and the challenges to intellectual property
The legal landscape of adopting AI now and in the future.
Worrying landscape for Welsh construction SMEs revealed.
In recent risk factor analysis report completed by CIOB.
Construction Sport survey highlights risks of dehydration
Supporting construction workers to avoid dangers.
Can your business afford to ignore mental well-being?
£70 - 100 billion annually in UK construction sector.
Mental health in the construction industry
World Mental Health Day 10 October.
Construction awards provide relief in wake of ISG collapse
Spike in major infrastructure awards, housing up but short of targets, are ISG collapse impacts yet to come.
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.