Tilt up construction
Contents |
[edit] Introduction
This cost-effective building technique can produce a shorter completion time for construction projects. The main aspect of tilt-up construction that makes it unique is the way that the concrete structural supports, columns, and walls are created. These elements are all formed on the ground and then tilted into a vertical position with the assistance of a crane.
[edit] The tilt-up construction process
Due to its complexity, the process for this type of construction requires significant planning and organisation. Specific steps must be taken to ensure success:
- Evaluating the site.
- Engineering.
- Creating footings and floor slabs.
- Forming the tilt-up panels.
- Placing inserts, embeds and steel grids inside each form.
- Spraying forms with bond breaker chemicals.
- Concrete pouring and placement.
- Erection of panels and panel finishing.
Once the concrete floor slab has cured, the process of creating wall sections can begin. Typically, fiber boards or high-quality plywood are used to create forms for a project. However, steel or aluminum forms can also be used. Engineered blueprints help guide carpenters so that they know how to construct each element. Architectural features are incorporated into each element as well as the openings for windows and doors. Important construction items like studs, attachment plates and gussets are placed inside each form in preparation for pouring concrete.
The next step is crucial as it ensures the new concrete casts do not bond with the floor slab. A special chemical spray is used on the surface of the forms. Without this critical step, costly damage could occur. It's important to properly apply the correct chemical during this process.
After the bond breaker spray is used, steel rebar is constructed into a grid pattern inside of each form. Once finished, concrete is poured into each form to meet the specifications dictated by the blueprints for the building. When the curing process has completed, the forms are removed. The last step involves the attachment of rigging onto each section so that a crane can tilt or lift each panel into place.
These tilt-up structures can be extremely heavy, weighing more than 100,000 pounds. Headed studs and steel plates are used to connect the newly-formed concrete structures with the floor and roof. Some of these concrete structures may be used on the inside of the building structure as sheer walls. This helps provide extra reinforcement for any upper floors and the roof.
Insulation can also be used on these concrete panels. One method is to place it between two concrete layers during the casting process or to apply it either side of the concrete panels after they've been erected. One advantage of this type of construction is that it is fire resistant. Also, during the design process, plans can be designed so that the concrete slabs sag inward, which helps minimize the possibility of a complete collapse.
[edit] Typical uses
Tilt-up construction was first being used in America during the early 1900s. However, erection of the concrete slabs was completed with the assistance of tilt tables instead of cranes. During the construction boom after World War II, the popularity of tilt-up construction began to spread.
Warehouses were the most popular buildings being built after the tilt-up process was first introduced. Today, many types of buildings are created using this technique, including; hotels, industrial sheds, houses, offices and schools, and they can be single-story or multi-story structures.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Government consultations for the summer of 2025
A year of Labour, past and present consultations on the environment, the built environment, training and tax.
CMA competitiveness probe of major housing developers
100 million affordable housing contributions committed with further consultation published.
Homes England supports Greencore Homes
42 new build affordable sustainable homes in Oxfordshire.
Zero carbon social housing: unlocking brownfield potential
Seven ZEDpod strategies for brownfield housing success.
CIOB report; a blueprint for SDGs and the built environment
Pairing the Sustainable Development Goals with projects.
Types, tests, standards and fires relating to external cladding
Brief descriptions with an extensive list of fires for review.
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.