Tilt up construction
Contents |
[edit] Introduction
This cost-effective building technique can produce a shorter completion time for construction projects. The main aspect of tilt-up construction that makes it unique is the way that the concrete structural supports, columns, and walls are created. These elements are all formed on the ground and then tilted into a vertical position with the assistance of a crane.
[edit] The tilt-up construction process
Due to its complexity, the process for this type of construction requires significant planning and organisation. Specific steps must be taken to ensure success:
- Evaluating the site.
- Engineering.
- Creating footings and floor slabs.
- Forming the tilt-up panels.
- Placing inserts, embeds and steel grids inside each form.
- Spraying forms with bond breaker chemicals.
- Concrete pouring and placement.
- Erection of panels and panel finishing.
Once the concrete floor slab has cured, the process of creating wall sections can begin. Typically, fiber boards or high-quality plywood are used to create forms for a project. However, steel or aluminum forms can also be used. Engineered blueprints help guide carpenters so that they know how to construct each element. Architectural features are incorporated into each element as well as the openings for windows and doors. Important construction items like studs, attachment plates and gussets are placed inside each form in preparation for pouring concrete.
The next step is crucial as it ensures the new concrete casts do not bond with the floor slab. A special chemical spray is used on the surface of the forms. Without this critical step, costly damage could occur. It's important to properly apply the correct chemical during this process.
After the bond breaker spray is used, steel rebar is constructed into a grid pattern inside of each form. Once finished, concrete is poured into each form to meet the specifications dictated by the blueprints for the building. When the curing process has completed, the forms are removed. The last step involves the attachment of rigging onto each section so that a crane can tilt or lift each panel into place.
These tilt-up structures can be extremely heavy, weighing more than 100,000 pounds. Headed studs and steel plates are used to connect the newly-formed concrete structures with the floor and roof. Some of these concrete structures may be used on the inside of the building structure as sheer walls. This helps provide extra reinforcement for any upper floors and the roof.
Insulation can also be used on these concrete panels. One method is to place it between two concrete layers during the casting process or to apply it either side of the concrete panels after they've been erected. One advantage of this type of construction is that it is fire resistant. Also, during the design process, plans can be designed so that the concrete slabs sag inward, which helps minimize the possibility of a complete collapse.
[edit] Typical uses
Tilt-up construction was first being used in America during the early 1900s. However, erection of the concrete slabs was completed with the assistance of tilt tables instead of cranes. During the construction boom after World War II, the popularity of tilt-up construction began to spread.
Warehouses were the most popular buildings being built after the tilt-up process was first introduced. Today, many types of buildings are created using this technique, including; hotels, industrial sheds, houses, offices and schools, and they can be single-story or multi-story structures.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.
Renovating Union Chain Bridge.
AI tools for planning, design, construction and management
A long, continually expanding list, any more to add?
Robots in the construction industry
From cultural characterisations to construction sites.
Empowering construction with AI integration
New horizons with a human touch.
Key AI related terms to be aware of
With explanations from the UK government.
A Better Hiring Toolkit for construction
Tooling up to hire under best practice standards in the sector.
Recharging Electrical Skills in Wales
Step by step collaborative solutions.