Comparison of standard project plans used in the construction industry
[edit] What is a plan of work?
A plan of work is an agreed system for classifying different stages in the lifecycle of projects to define, design, construct, operate and decommission built assets. It is important to be clear about the exact definition of project stages as these can be used to establish gateways were decisions are made about whether to proceed with a project, as well as payment points and contractual milestones.
Unfortunately the construction industry has not settled on a single plan of work, and this is very confusing both within the industry and for those working with the industry, such as clients.
This article began by mapping the project stages set out in the RIBA Plan of Work (2007) v the RIBA Plan of Work (2013) v the Designing Buildings Wiki Project Plans v the OGC gateway review process. It has since expanded and developed as different project plans have been published and updated.
[edit] RIBA plan of work 2007 v 2013 v OGC Gateways
The differences between, and areas of similarity between, the RIBA plan of work 2007 v 2013 v OGC Gateways are set out below. These are compared with the plan of work created for Designing Buildings, which places greater emphasis on the crucial early stages of the project when important decisions are made about its nature and scope and whether it should proceed at all. The RIBA plan of work gives undue (but understandable) emphasis on the design stages, which may be less important to the client.
[edit] 2020 RIBA Plan of Work
In 2020, the RIBA Plan of Work stages were changed to:
- 0 - Strategic definition.
- 1 - Preparation and briefing.
- 2 - Concept design.
- 3 - Spatial coordination.
- 4 - Technical design.
- 5 - Manufacturing and construction.
- 6 - Handover.
- 7 - Use.
[edit] BIM Task Group Digital Plan of Work
The 2014 BIM Task Group Digital Plan of Work was based on:
- 0 Strategy
- 1 Brief
- 2 Concept
- 3 Definition
- 4 Design
- 5 Build and commission
- 6 Handover and close-out
- 7 Operation and end-of-life
[edit] Construction Industry Council scope of services
The 2007 Construction Industry Council (CIC) scope of services adopted:
- Stage 1 (Preparation)
- Stage 2 (Concept)
- Stage 3 (Design Development)
- Stage 4 (Production Information)
- Stage 5 (Manufacture, Installation & Construction Information)
- Stage 6 (Post Practical Completion)
[edit] The Construction Playbook
The 2022 Construction Playbook, published by HM Government, adopted:
- Preparation and planning.
- Publication.
- Selection.
- Evaluation and award.
- Contract implementation.
[edit] ISO 19650-2
ISO 19650-2, publsuhed in 2018 adopted:
- Assessment of need.
- Invitation to tender.
- Tender response.
- Appointment.
- Mobilization.
- Collaborative production of information.
- Information model delivery.
- Project close out.
[edit] Soft Landings Framework
The 2018 Soft Landings Framework adopted:
- Inception and briefing.
- Design.
- Construction.
- Pre-handover.
- Initial aftercare.
- Extended aftercare and post occupancy evaluation.
[edit] Plans of work for infrastructure
The nature of infrastructure projects can be different to projects buildings, and so they have tended to adopt their own plans of work.
[edit] The importance of defining the plan of work
Given the complexity of this situation and the potential for misunderstanding the nature of what is meant by different project stages it is important that appointment documents and contracts set out precisely what is required, and at what level of detail for different stages of a project rather than relying on reference to ambiguous names or process maps.
[edit] Related articles on Designing Buildings
- Stage 1: Business justification.
- Stage 2: Feasibility studies.
- Stage 3: Project brief.
- Stage 4: Concept design.
- Stage 5: Detailed design.
- Stage 6: Production information.
- Stage 7: Tender.
- Stage 8: Mobilisation.
- Stage 9: Construction.
- Stage 10: Occupation and defects liability period.
- Stage 11: Post occupancy evaluation.
- BREEAM and RIBA stages.
- Comparison of BIM work stages.
- Design phase.
- Designing Buildings Wiki project plans.
- Gateway.
- Governance for Railway Investment Projects (GRIP).
- nbs.
- OGC gateway review process.
- Project lifecycle for major road projects.
- RIBA.
- RIBA plan of work.
Featured articles and news
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Comments
To make a comment about this article, click 'Add a comment' above.
Separate your comments from any existing comments by inserting a horizontal line.
please, what are the differences between RIBA plan of work and GRIP
Why cant the industry settle on one plan and just stick to it. Constant change is confusing for everyone.