Project lifecycle for major road projects
Contents |
[edit] Introduction
The project control framework (PCF) is a joint Department for Transport and Highways Agency approach to managing major projects, which comprises:
- A standard project lifecycle.
- Standard project deliverables.
- Project control processes.
- Governance arrangements.
The project lifecycle for major road projects is set out in the project control framework Handbook v2 April 2013.
Once initiated a project enters the major projects lifecycle which breaks down the three phases of the project control framework into seven stages shown below:
[edit] Major projects lifecycle
[edit] Pre-project
0: Strategy, shaping and prioritisation
[edit] Options phase
1: Option identification
- Identify options to be taken to public consultation.
- Assess options in terms of environmental impact, traffic forecasts and economic benefits.
- Refine the cost estimate of options (including an allowance for risk).
2: Option selection
- Carry out public consultation including exhibitions.
- Analyse comments received and select a preferred option.
- Refine the cost estimate for preferred option (including allowance for risk).
- Refine the environmental impact assessment, traffic forecasts, and economic benefits following public consultation if required.
- Produce an outline business case.
- Announce the preferred route.
[edit] Development phase
- If early contractor involvement procurement method selected, appoint contractor.
- Carry out surveys (such as topographical, geotechnical, environmental).
- For Planning Act 2008 schemes hold community consultation including exhibitions, complete consultation report and resolve or rebut outstanding issues.
- Complete and freeze the preliminary design of the preferred route.
- Prepare draft Planning Act 2008 development consent order (or Highways Act 1980 orders if the scheme is below the threshold for a nationally significant infrastructure project (NSIP)), as appropriate.
- Complete the environmental assessment and prepare the environmental statement.
- Agree initial target cost with ECI contractor (if applicable).
4: Statutory procedures and powers
- Publish notice of acceptance of Planning Act 2008 draft development consent order and application (or notice of draft Highways Act 1980 orders if the scheme is below the threshold for a NSIP) and environmental statement as appropriate (exhibitions may be considered for Highways Act 1980 orders).
- Arrange public inquiry for Highways Act 1980 orders (if required).
- Under the Planning Act 2008 the Planning Inspectorate will decide on the preliminary meeting and examination of the application for development consent. We will need to register and comment as an interested party (the developer).
- Present evidence and rebuttals to objections for Highways Act 1980 orders at inquiry.
- The Planning Inspectorate panel or inspector will make recommendations to the Secretary of State.
- Issue secretary of state’s decision letter confirming whether orders/development consent are to be confirmed as published in draft, rejected or amended.
5: Construction preparation
- Confirm orders/development consent and respond to any high court challenges (if any).
- Obtain approval to any advance works or advance statutory undertakers diversions.
- Agree costs of construction with the contractor. If ECI is procurement method, agree final target cost.
- Produce the final business case.
- For Planning Act 2008 schemes place details of land to be acquired on deposit and publish a notice to say where these can be inspected.
- Obtain notice to proceed
[edit] Construction phase
6: Construction, commissioning and handover
- Issue notices to treat and enter take possession of land.
- Complete detailed design.
- Construct and commission scheme.
- Hand over asset for operation with as-built drawings and health and safety file.
- Open scheme to traffic.
7: Closeout
- Agree final account with contractor.
- Contractor completes outstanding works (or re-work).
- Complete a review of project.
[edit] Related articles on Designing Buildings Wiki
- Comparison of BIM work stages.
- Designing Buildings Wiki project plans.
- Gateway.
- Governance for Railway Investment Projects (GRIP).
- Great Musgrave: infilled bridge a sad reflection on state of the industry.
- OGC gateway review process.
- RIBA plan of work.
- RIBA plan of work v project plans v OGC gateways.
Featured articles and news
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.