Project lifecycle for major road projects
Contents |
[edit] Introduction
The project control framework (PCF) is a joint Department for Transport and Highways Agency approach to managing major projects, which comprises:
- A standard project lifecycle.
- Standard project deliverables.
- Project control processes.
- Governance arrangements.
The project lifecycle for major road projects is set out in the project control framework Handbook v2 April 2013.
Once initiated a project enters the major projects lifecycle which breaks down the three phases of the project control framework into seven stages shown below:
[edit] Major projects lifecycle
[edit] Pre-project
0: Strategy, shaping and prioritisation
[edit] Options phase
1: Option identification
- Identify options to be taken to public consultation.
- Assess options in terms of environmental impact, traffic forecasts and economic benefits.
- Refine the cost estimate of options (including an allowance for risk).
2: Option selection
- Carry out public consultation including exhibitions.
- Analyse comments received and select a preferred option.
- Refine the cost estimate for preferred option (including allowance for risk).
- Refine the environmental impact assessment, traffic forecasts, and economic benefits following public consultation if required.
- Produce an outline business case.
- Announce the preferred route.
[edit] Development phase
- If early contractor involvement procurement method selected, appoint contractor.
- Carry out surveys (such as topographical, geotechnical, environmental).
- For Planning Act 2008 schemes hold community consultation including exhibitions, complete consultation report and resolve or rebut outstanding issues.
- Complete and freeze the preliminary design of the preferred route.
- Prepare draft Planning Act 2008 development consent order (or Highways Act 1980 orders if the scheme is below the threshold for a nationally significant infrastructure project (NSIP)), as appropriate.
- Complete the environmental assessment and prepare the environmental statement.
- Agree initial target cost with ECI contractor (if applicable).
4: Statutory procedures and powers
- Publish notice of acceptance of Planning Act 2008 draft development consent order and application (or notice of draft Highways Act 1980 orders if the scheme is below the threshold for a NSIP) and environmental statement as appropriate (exhibitions may be considered for Highways Act 1980 orders).
- Arrange public inquiry for Highways Act 1980 orders (if required).
- Under the Planning Act 2008 the Planning Inspectorate will decide on the preliminary meeting and examination of the application for development consent. We will need to register and comment as an interested party (the developer).
- Present evidence and rebuttals to objections for Highways Act 1980 orders at inquiry.
- The Planning Inspectorate panel or inspector will make recommendations to the Secretary of State.
- Issue secretary of state’s decision letter confirming whether orders/development consent are to be confirmed as published in draft, rejected or amended.
5: Construction preparation
- Confirm orders/development consent and respond to any high court challenges (if any).
- Obtain approval to any advance works or advance statutory undertakers diversions.
- Agree costs of construction with the contractor. If ECI is procurement method, agree final target cost.
- Produce the final business case.
- For Planning Act 2008 schemes place details of land to be acquired on deposit and publish a notice to say where these can be inspected.
- Obtain notice to proceed
[edit] Construction phase
6: Construction, commissioning and handover
- Issue notices to treat and enter take possession of land.
- Complete detailed design.
- Construct and commission scheme.
- Hand over asset for operation with as-built drawings and health and safety file.
- Open scheme to traffic.
7: Closeout
- Agree final account with contractor.
- Contractor completes outstanding works (or re-work).
- Complete a review of project.
[edit] Related articles on Designing Buildings Wiki
- Comparison of BIM work stages.
- Designing Buildings Wiki project plans.
- Gateway.
- Governance for Railway Investment Projects (GRIP).
- Great Musgrave: infilled bridge a sad reflection on state of the industry.
- OGC gateway review process.
- RIBA plan of work.
- RIBA plan of work v project plans v OGC gateways.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.

























