Traditional contract: feasibility studies
The feasibility studies stage considers the options for satisfying the client's needs, enabling the client to prepare a business case for the preferred option and deciding whether to proceed with the project. It is possible to make an outline planning application during this stage if the risk to the project of not receiving planning permission is high, or if delays in receiving planning permission would be problematic.
Contents |
[edit] Appointing a consultant team
The client updates the preliminary business case and strategic brief to reflect comments made at the end of the previous stage and collates site information ready to issue to the consultant team.
The client appoints the consultant team and other advisers (such as independent client advisers). See work stage: Traditional contract: appointment.
The client chairs a consultant team start-up meeting to issue information to the consultant team. This is also an opportunity to establish collaborative practices and agree a programme.
The principal designer (if appointed) confirms with the client that they are aware of their duties under the CDM regulations.
[edit] Developing the strategic brief.
The consultant team work with the client to help them develop the strategic brief sufficiently for feasibility studies and options appraisals to be carried out.
The consultant team assess the site information issued to them by the client and undertake site appraisals. The consultant team obtain any further information about the site that might be required to undertake feasibility studies, such as; site surveys, information about site services, site access conditions, legislative constraints, existing planning consents etc. Where necessary, approval should be sought from the client (for example site surveys requiring additional expenditure).
The lead consultant co-ordinates the preparation of feasibility studies to establish whether the project is viable, and to identify feasible options. The client considers the feasibility studies, and agrees which options the consultant team should develop.
[edit] Preparing an options review report.
The lead designer co-ordinates identification of any further site surveys or site information required to carry out options appraisals and where appropriate seeks approval from the client.
The lead consultant co-ordinates the preparation of a draft options review report:
- The lead designer co-ordinates the preparation of diagrammatic options studies.
- The principal designer (if appointed at this stage) assesses the risks of the options in relation to the CDM regulations.
- The architect co-ordinates consultations with the local authority and other statutory authorities and assesses possible planning permission requirements and other statutory requirements (such as the need for an environmental impact assessment for the options). NB See the work stage Traditional contract: planning permission for additional information.
- The cost consultant prepares initial cost appraisals of the options.
The client considers the draft options review report and either selects a preferred option or instructs the lead consultant to revise the options review report.
[edit] Preparing a business case and project execution plan.
The lead consultant co-ordinates further assessment of the preferred option to assist the client in preparing a business case and project execution plan, including:
- The lead designer establishes requirements for statutory approvals and other regulations with which the preferred option must comply.
- The lead designer co-ordinates consultations with utility providers.
- The lead consultant co-ordinates an assessment of the need for specialist advice to develop the preferred option and advises the client.
With the benefit of assessments carried out by the consultant team, the client develops the preliminary business case into a full business case and project execution plan for the preferred option.
The client considers, and if appropriate, approves the business case and project execution plan for the preferred option and gives instructions to proceed to the next stage along with any other instructions that may be necessary.
At this stage, the client, lead designer and architect may consider whether it would be appropriate to make an outline planning application for the proposed development and direct the consultant team accordingly (if an outline planning application is required at this stage, go to the work stage: Traditional contract: planning permission).
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.