Options appraisals for construction projects
Options appraisals are undertaken following the completion of feasibility studies. Their purpose is to assess a number of potential options before developing a concept design for the preferred option.
After assessing the feasibility studies, the client will decide which options the consultant team should develop. Ideally there will be no more than four options at this stage. If more options exist it may be necessary to carry out further high-level studies before proceeding to more detailed options appraisals.
Options appraisals might include diagrammatic options studies that enable the client to understand the broad pros and cons of the available options so that a preferred option can be selected.
These studies allow further assessments and discussions:
- An assessment of the risks of the options.
- Consultations with the local authority and other statutory authorities, to assesses possible planning permission requirements and other statutory requirements (such as the need for an environmental impact assessment for the options).
- Initial cost appraisals of the options.
Preparing appraisals may require further site surveys or site information. It may also be necessary to commission additional advice, such as planning advice, expertise on rights of light, engineering advice, or other specialist services depending on the complexity of the project. The need to commission other consultants will often be determined by the scale and location of a development and also by the client’s familiarity with the site and the local area. A large-scale development with underground constraints will almost certainly require engineering expertise in the early stages, whereas a residence in a traditional street may not. Both however may require an understanding of local authority or other statutory consultee positions.
The lead consultant can then co-ordinate the preparation of an options review report, from which the client can either select a preferred option or instruct the development of further options or appraisals.
The options review report might contain:
- A general description of the options.
- Diagrammatic sketch layouts.
- The overall consequences of each option for the client's operations.
- Assessment of compatibility with the clients vision, mission and objectives.
- Assessment of the overall feasibility of each option.
- Potential for future-proofing.
- Planning permission issues (including the potential requirement for an environmental impact assessment).
- Sustainability considerations.
- Impact on the local community and environment.
- Third-party dependencies.
- Value management exercises.
- Whole-life costs with a rudimentary assessment of costs/sqm, configuration and servicing.
- Time-frames, phasing and key milestones.
- Procurement route.
- Risks.
- Recommendations.
At this stage the client’s brief is likely to expand, partly from the conclusions of the appraisals but also from knowledge gained by research into planning precedents, legal issues, engineering data and the technical constraints and nature of the project.
Wherever possible, any information prepared or obtained should be in a format which can be readily shared and used, and should be stored and named in a way consistent with the long-term project and operational needs.
Once a preferred option has been selected, the consultant team may carry out further assessments to assist the client in preparing a business case and project execution plan for the preferred option before concept design begins.
[edit] Related articles
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.