Key contractual clauses
Here is s short list looking at some key clauses that might be found in a construction contract:
- Scope of work : This clause clearly outlines the project's objectives, deliverables, and specifications. It's essential to prevent "scope creep," where additional tasks are added without proper compensation.
- Payment terms : This clause specifies how and when payments are made throughout the project. It should detail payment schedules, retainage, and how to handle progress payments or milestones.
- Change Orders: This clause outlines the process for making changes to the original scope of work. It should address how changes are approved, documented, and how costs are adjusted.
- Dispute resolution : This clause specifies the process for handling disagreements. It may involve mediation, arbitration, or litigation, and should be tailored to the specific project and jurisdiction.
- Termination Conditions : This clause defines the conditions under which the contract can be terminated by either party. It's crucial for protecting rights and managing risk in various scenarios.
- Insurance and Liability : This clause clarifies who is responsible for risks, delays, and damages on the construction site. It's essential to ensure adequate insurance coverage and liability protection.
- Force majeure : This clause addresses unforeseen events that prevent a party from fulfilling their contractual obligations. It should be carefully drafted to cover various scenarios like pandemics or natural disasters.
- Delay and Extension of Time (EOT) : This clause deals with project delays. It defines what constitutes an excusable delay and how extensions of time are granted.
- Variations: This clause addresses the process for making changes to the original scope of work or the contract.
[edit] Related articles on Designing Buildings
- Addendum.
- Alternative dispute resolution.
- Articles of agreement.
- Common law.
- Competitive procedure with negotiation.
- Condition.
- Construction contract.
- Construction law.
- Contract administrator.
- Contract negotiations.
- Contract strategy.
- Contractual right.
- Delay damages.
- Disallowed cost.
- Escalation.
- Essentials of a contract.
- Excepted risk.
- Extension of time.
- Form of tender.
- Hybrid construction contract.
- Key dates.
- Liquidated damages.
- Loss and expense.
- Modifying clauses in standard forms of contract.
- Named specialist work.
- Negotiated Procedure without Prior Publication NPwPP.
- Outturn cost.
- Payment for extra work.
- Pre-contract management.
- Proprietary information.
- Quantum meruit.
- Right to payment.
- Supply chain management.
- Variation.
- Z clauses.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.

















