Design and build procurement route

ConstructionSafety.jpg

Key takeaways:

The Design and Build (D&B) procurement route is a project delivery method where a single contractor is responsible for both design and construction. This approach streamlines project management, often leading to faster completion and better cost certainty. It is the most commonly used procurement method in the UK, accounting for over 50% of projects. While D&B offers a single point of responsibility, it can limit client control over design details. It is ideal for projects where speed, efficiency, and cost control are priorities, but may not suit those requiring highly customised design input.

Contents

[edit] What is the design and build procurement route?

Design and build is a procurement route in which the main contractor is appointed to both design and then construct the works described in the contract. This is as opposed to the traditional procurement route, in which the client first appoints consultants to design the development and then a contractor is appointed to construct the works.

Design and build can be seen as giving a single point of responsibility for delivering the entire project. Some clients, however, consider it is only appropriate for simple projects, where design quality is not the main consideration.

The traditional procurement route was historically the most commonly used procurement route, but there has been an increasing trend for contractors to take a more significant role in setting up projects, making appointments and managing the entire project process. This began with the introduction of design and build, which became popular in the 1980s.

[edit] How popular is the design and build procurement route?

The Procurement Trends Report, published by Ryder Levett Bucknall (RLB) in 2024, found that 67% of projects now use design and build forms of contract, the highest proportion recorded since RLB's survey began. This builds on the trend identified in RLB's March 2022 survey, in which design and build accounted for 54% of projects, and confirms design and build as by far the most commonly-used procurement route in the UK.

[edit] How does the design and build procurement route work?

The employer gives potential contractors their 'employer's requirements' setting out what they need from the project, and the contractors respond with 'contractor's proposals', which include a price for the works.

The contractor can either be appointed to carry out all of the design work, or if the client wishes to have greater influence over the design, a concept design and outline (or performance) specification can be prepared by a consultant employed by the client, and then the contractor is appointed to complete the design and carry out the construction.

The contractor may use their own in-house designers to design the building, or they can appoint consultant designers, or the client's designers can be employed by the contractor to complete the design (either by novation or consultant switch).

Design and build contracts can be awarded on a fixed price, lump sum basis, but price certainty is then dependent on not making any subsequent changes as these could prove to be expensive (as prices charged by the contractor for those changes will not be subject to competition).

It is very important therefore that the client gives a great deal of consideration to the preparation of the employer's requirements, and if they have not appointed their own design team, they may wish to appoint independent client advisers to help them do this. Similarly, if any designers appointed by the client are novated or switched to work for the contractor, the client may then wish to appoint independent client advisers to review contractor's design proposals, administer the contract and monitor works on site.

[edit] What are the different types of design and build?

There are two main types of design and build:

[edit] What is single-stage design and build?

In the single-stage process the contractor is appointed under a single agreement to undertake the design and then construct the works. Single-stage tendering is used when all the information necessary to calculate a realistic price is available when tendering commences.

[edit] What is two stage design and build?

In a two-stage process the contractor is first selected on the basis of a fee, preliminaries, overheads and profit. They then work with the design team (who may be employed either by the contractor or by the client at this stage) to develop the design, on the basis of which a fixed price is negotiated for the second stage; construction, when the design team may be novated to the contractor if the contractor does not already employ them.

For more information see: Two-stage tender.

[edit] When should the design and build procurement route be used?

The design and build procurement route should be used:

[edit] What are the advantages of the design and build procurement route?

Advantages of the design and build procurement route include:

[edit] What are the disadvantages of the design and build procurement route?

Disadvantages of the design and build procurement route include:

See also: Design and build - pros and cons.

[edit] What types of contract can be used for the design build procurement route?

Design and build contracts include:

[edit] Notes

[edit] Related articles on Designing Buildings

[edit] External references

Comments

To make a comment about this article, click 'Add a comment' above.

Separate your comments from any existing comments by inserting a horizontal line.


What a useful and detailed website this is. Thank you!

Designing Buildings Anywhere

Get the Firefox add-on to access 20,000 definitions direct from any website

Find out more Accept cookies and
don't show me this again