Procurement route options pros and cons
This article needs more work. To help develop this article, click 'Edit this article' above.
See also: procurement route.
Contents |
[edit] Traditional contract
Good for:
- Quality – full design pre tender
- Design flexibility – variations & instructions
- Specialist subcontractors – Named specialist update to standard building contract sbc11
- Design control – through the architect / contract administrator
- Contractor's Designed Portion – such as mechanical and electrical engineering
- Cost – there may be lump sum cost benefits unless are multiple changes made
Not suited for:
- Time – require full detailed pack pre tender
- Cost – not a benefit if many changes made post tender
- Incomplete drawings – lead to delay, costs and claims of negligence
Contracts: JCT Standard Building Contract 2016, JCT Intermediate Building Contract 2016, JCT Minor Works Building Contract 2016, NEC3 ECC Option A
JCT Standard Building Contract 2016:
- Lump sum payment
- CDM
- Contractor's Designed Portion
- Named subcontractors
- Variations / instructions
- Retention
- Collateral warranties
- Termination provisions
- Pre-agreed alternative dispute resolution procedures.
[edit] Design and build
Good for:
- Time – Fast track, overlap of design and construction
- Cost – lump sum / Guaranteed maximum price
- Single point of responsibility – Contractor design and build responsibility
- Has good price certainty
- Novation – can benefit quality.
- Low risk for the client
- Variations can be accurately valued
Not suited for:
- Quality – cheapest route to meet contract specification can lead to low quality products/ build quality.
- Design flexibility – request for changes will have cost/time implications
- Contractor carries risk for construction
- Client exposed to claims for buildability
- Design could affect the buildability of the project
Contract: JCT Design and Build 2016, JCT Major Project Construction Contract 2016, NEC ECC Options A-E
JCT Design and Build 2016:
- Contractor to complete design and carry out the works.
- Lump sum / Guaranteed maximum price
- CDM
- Collateral warranties
- Termination provisions
- Retention
- Pre-agreed dispute resolution procedures
[edit] Management contracting
Good for:
- Complex / specialist projects – individually appointed packages to best suited sub-contractor
- Potential cost saving – competitive tender
- Time - it is possible to overlap design and construction
- Quality – each package subcontracted to specialist
- Design flexibility – changes can be made throughout construction, although there are potential cost implications.
Not suited for:
- Inexperienced clients – risk high
- Fixed cost - Prime cost basis per package.
- Lack of available specialists – would leave gaps in work to be undertaken.
Contract: JCT Management Building Contract 2016
- Prime cost contract
- Collateral warranties
- Sustainability
- Collaborative working
- Third party rights – such as the funder / contractor
[edit] Construction management
Good for:
- Complex / specialist projects – individually appointed packages to best suited sub-contractor
- Time - It is possible to overlap design and construction
- Design flexibility – changes can be made throughout construction, although there are potential cost implications.
- Potential cost saving – competitive tender
- Quality – each package subcontracted to specialist
- All building types
- Efficiency – Early appointment of the construction manager to aid programme
- Inexperienced client – risk high as appointing trade contractors
- Fixed cost - Prime cost basis per package.
- Lack of available specialists
Contracts:
JCT Construction Management Appointment 2016, NEC ECC Option F, Construction Management Trade Contract 1999
JCT Construction Management Appointment 2016:
CM/A
Featured articles and news
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.
A brief run down of changes intentions from April in an onwards.
Reslating an ancient water mill
A rare opportunity to record, study and repair early vernacular roofs.
CIOB Apprentice of the Year 2025/26
Construction apprentice from Lincoln Mia Owen wins this years title.
Insulation solutions with less waste for a circular economy
Rob Firman, Technical and Specification Manager, Polyfoam XPS explains.
Recycled waste plastic in construction
Hierarchy, prevention to disposal, plastic types and approaches.
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.























Comments
This article seems to need some revision: The Management Contracting and Construction Management procurement methods appear to be the wrong way round.
Construction Management is far higher risk than Management Contracting for the client.
The end of the article also doesn't seem to be consistent with the 'suitable for' and 'not suitable for'.
So change it - its a wiki site.