Procurement route options pros and cons
This article needs more work. To help develop this article, click 'Edit this article' above.
See also: procurement route.
Contents |
[edit] Traditional contract
Good for:
- Quality – full design pre tender
- Design flexibility – variations & instructions
- Specialist subcontractors – Named specialist update to standard building contract sbc11
- Design control – through the architect / contract administrator
- Contractor's Designed Portion – such as mechanical and electrical engineering
- Cost – there may be lump sum cost benefits unless are multiple changes made
Not suited for:
- Time – require full detailed pack pre tender
- Cost – not a benefit if many changes made post tender
- Incomplete drawings – lead to delay, costs and claims of negligence
Contracts: JCT Standard Building Contract 2016, JCT Intermediate Building Contract 2016, JCT Minor Works Building Contract 2016, NEC3 ECC Option A
JCT Standard Building Contract 2016:
- Lump sum payment
- CDM
- Contractor's Designed Portion
- Named subcontractors
- Variations / instructions
- Retention
- Collateral warranties
- Termination provisions
- Pre-agreed alternative dispute resolution procedures.
[edit] Design and build
Good for:
- Time – Fast track, overlap of design and construction
- Cost – lump sum / Guaranteed maximum price
- Single point of responsibility – Contractor design and build responsibility
- Has good price certainty
- Novation – can benefit quality.
- Low risk for the client
- Variations can be accurately valued
Not suited for:
- Quality – cheapest route to meet contract specification can lead to low quality products/ build quality.
- Design flexibility – request for changes will have cost/time implications
- Contractor carries risk for construction
- Client exposed to claims for buildability
- Design could affect the buildability of the project
Contract: JCT Design and Build 2016, JCT Major Project Construction Contract 2016, NEC ECC Options A-E
JCT Design and Build 2016:
- Contractor to complete design and carry out the works.
- Lump sum / Guaranteed maximum price
- CDM
- Collateral warranties
- Termination provisions
- Retention
- Pre-agreed dispute resolution procedures
[edit] Management contracting
Good for:
- Complex / specialist projects – individually appointed packages to best suited sub-contractor
- Potential cost saving – competitive tender
- Time - it is possible to overlap design and construction
- Quality – each package subcontracted to specialist
- Design flexibility – changes can be made throughout construction, although there are potential cost implications.
Not suited for:
- Inexperienced clients – risk high
- Fixed cost - Prime cost basis per package.
- Lack of available specialists – would leave gaps in work to be undertaken.
Contract: JCT Management Building Contract 2016
- Prime cost contract
- Collateral warranties
- Sustainability
- Collaborative working
- Third party rights – such as the funder / contractor
[edit] Construction management
Good for:
- Complex / specialist projects – individually appointed packages to best suited sub-contractor
- Time - It is possible to overlap design and construction
- Design flexibility – changes can be made throughout construction, although there are potential cost implications.
- Potential cost saving – competitive tender
- Quality – each package subcontracted to specialist
- All building types
- Efficiency – Early appointment of the construction manager to aid programme
- Inexperienced client – risk high as appointing trade contractors
- Fixed cost - Prime cost basis per package.
- Lack of available specialists
Contracts:
JCT Construction Management Appointment 2016, NEC ECC Option F, Construction Management Trade Contract 1999
JCT Construction Management Appointment 2016:
CM/A
Featured articles and news
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?
The Architectural Technology podcast: Where it's AT
Catch-up on the latest episodes.
Edmundson Apprentice of the Year award 2026
Entries now open for this Electrical Contractors' Association award.
Traditional blue-grey slate from one of the oldest and largest UK slate quarries down in Cornwall.
There are plenty of sources with the potential to be redeveloped.
Change of use legislation breaths new life into buildings
A run down on Class MA of the General Permitted Development Order.
Solar generation in the historic environment
Success requires understanding each site in detail.
























Comments
This article seems to need some revision: The Management Contracting and Construction Management procurement methods appear to be the wrong way round.
Construction Management is far higher risk than Management Contracting for the client.
The end of the article also doesn't seem to be consistent with the 'suitable for' and 'not suitable for'.
So change it - its a wiki site.