Minor works
The phrase ‘minor works’ refers to small, relatively straight-forward construction projects, typically less than £500,000 in value.
In particular the phrase is used in relation to the Joint Contracts Tribunal (JCT) Minor Works Building Contract. This contract follows the traditional procurement route, where first the design is completed, and then a contractor is appointed to construct the works. JCT do not set a limit for the minor works building contract in terms of value, but typically it will be used on projects of less than £250,000.
More important than value in determining whether this is an appropriate form of contract is the nature of the project.
It can be used for projects where:
- The project is fairly simple.
- The project should last no more than 12 months.
- The client is responsible for procuring the design, including drawings, a specification, or work schedules.
- Or the contractor is responsible for designing specific parts of the works (Minor Works Building Contract with contractor’s design).
It is not suitable where:
- The project is more complex.
- The project design includes bills of quantities.
- The project has detailed control procedures.
- The project has multiple phases or sections.
- There are provisions to govern work carried out by named specialists.
The JCT Minor Works Building Contract is more straight forward to administer than many other forms of contract, however, the parties will still need to be very clear of their obligations and liabilities and the risks that they are accepting. Generally the client’s architect or contract administrator will administer the contract.
Other standard forms of minor works contract are available. The New Engineering Contract (NEC) states that its contracts can be used for minor works, and the Federation of Master Builders publishes a freely available suite of minor works contracts.
The Institution of Civil Engineers (ICE) and the Government Conditions of contract (GC Works) contracts have now been withdrawn in favour of NEC contracts.
NB Safety at Street Works and Road Works, A Code of Practice, published by Department for Transport in October 2013, defines minor works as: ‘works with a planned duration of three days of less, excluding immediate or major works.’
[edit] Related articles on Designing Buildings
- Causes of construction disputes.
- Construction contracts.
- Contract claims.
- JCT.
- JCT Design and Build Contract.
- JCT Sub-subcontract.
- Modifying clauses in standard forms of construction contract.
- NEC contract.
- Procurement route.
- Repair and maintenance contract.
- RIBA Concise Building Contract.
- RIBA Domestic Building Contract.
- Standard Building Contract.
- Traditional contract.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.