Minor works
The phrase ‘minor works’ refers to small, relatively straight-forward construction projects, typically less than £500,000 in value.
In particular the phrase is used in relation to the Joint Contracts Tribunal (JCT) Minor Works Building Contract. This contract follows the traditional procurement route, where first the design is completed, and then a contractor is appointed to construct the works. JCT do not set a limit for the minor works building contract in terms of value, but typically it will be used on projects of less than £250,000.
More important than value in determining whether this is an appropriate form of contract is the nature of the project.
It can be used for projects where:
- The project is fairly simple.
- The project should last no more than 12 months.
- The client is responsible for procuring the design, including drawings, a specification, or work schedules.
- Or the contractor is responsible for designing specific parts of the works (Minor Works Building Contract with contractor’s design).
It is not suitable where:
- The project is more complex.
- The project design includes bills of quantities.
- The project has detailed control procedures.
- The project has multiple phases or sections.
- There are provisions to govern work carried out by named specialists.
The JCT Minor Works Building Contract is more straight forward to administer than many other forms of contract, however, the parties will still need to be very clear of their obligations and liabilities and the risks that they are accepting. Generally the client’s architect or contract administrator will administer the contract.
Other standard forms of minor works contract are available. The New Engineering Contract (NEC) states that its contracts can be used for minor works, and the Federation of Master Builders publishes a freely available suite of minor works contracts.
The Institution of Civil Engineers (ICE) and the Government Conditions of contract (GC Works) contracts have now been withdrawn in favour of NEC contracts.
NB Safety at Street Works and Road Works, A Code of Practice, published by Department for Transport in October 2013, defines minor works as: ‘works with a planned duration of three days of less, excluding immediate or major works.’
[edit] Related articles on Designing Buildings
- Causes of construction disputes.
- Construction contracts.
- Contract claims.
- JCT.
- JCT Design and Build Contract.
- JCT Sub-subcontract.
- Modifying clauses in standard forms of construction contract.
- NEC contract.
- Procurement route.
- Repair and maintenance contract.
- RIBA Concise Building Contract.
- RIBA Domestic Building Contract.
- Standard Building Contract.
- Traditional contract.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.

















