JCT Design and Build Contract
The Joint Contracts Tribunal (JCT) Design and Build Contract (DB) is intended for use on construction projects following the design and build procurement route. This involves appointing a main contractor to design (or complete the design) of the project and then to go on and construct it. This is as opposed to the traditional procurement route in which the client appoints consultants to design the project and then a contractor is appointed to construct it.
Design and build gives a single point of responsibility for delivering the entire project, and can help ensure good buildability, cost control and speed. Some clients however, consider it is only appropriate for simple projects, where retaining control over the design is not the main priority.
The scale and complexity of design and build projects can vary considerably, but the DB contract is generally suitable for projects where a detailed agreement is required, making provision for collaborative working, sustainability, advance payment, third party rights, bonds, collateral warranties and so on.
The 2016 edition of the contract includes the following documents:
- Design and Build contract guide (DB/G).
- Design and Build sub-contract agreement (DBSub/A).
- Design and Build sub-contract conditions (DBSub/C).
- Short form of sub-contract (ShortSub): For small-scale subcontract works that are simple and involve low risk.
- Sub-subcontract (SubSub).
- Design and Build sub-contract guide (DBSub/G).
- Design and Build contract (DB) Tracked Change Document: Highlights the changes between the DB 2011 and 2016 editions.
[edit] Related articles on Designing Buildings Wiki
- Construction contract.
- Construction management contract.
- Design and build.
- Design and build - pros and cons.
- Intermediate building contract.
- JCT.
- JCT minor works building contract.
- JCT Sub-subcontract.
- Major project construction contract.
- Management Building Contract.
- Prime cost contract.
- Standard Building Contract.
Featured articles and news
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
Comments
If the design build contractor is the actual designer and is responsible to procure the materials but not required to build. Can he change the material prices after signing the contract
What does the contract say - does it allow them to change prices? eg are fluctuations allowed?