Crane regulations
Contents |
[edit] Introduction
Cranes are a very common feature on construction projects. All lifting operations should be planned carefully so they are carried out safely having assessed all the risks, and there are a number of regulations and safety guidelines that must be adhered to.
The two principal hazards associated with cranes are the collapse of the crane and loads falling from height, both of which present significant potential for injury, fatalities and damage, both on and off-site.
In April 2013, following a public consultation, the Notification of Conventional Tower Crane Regulations 2010 were revoked, meaning that there is now no longer a duty to notify tower cranes on construction sites to the HSE.
Nonetheless, it is still a legal requirement that all operations involving lifting equipment must be properly planned by a competent person, appropriately supervised, and carried out in a safe manner. Crane operators, and those directing lifting operations, must be trained and competent. Cranes must be of adequate strength, tested at prescribed intervals, and subject to the required examinations and inspections as laid out in BS 7121:1:2006 Code of practice for safe use of cranes.
In addition, the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) place duties on people and companies who own, operate or have control over lifting equipment.
[edit] CPA contract
Crane hire companies adhere to the terms and conditions of the Construction Plant Hire Association (CPA) and in accordance with BS 7121 The Safe Use of Cranes.
Under the terms of a standard CPA crane hire contract, the client hires the crane and operator. The client takes full responsibility for the execution of the lifting operation as well as the crane once it is brought onto the site. The client must have an Appointed Person who is made responsible for the lift and provide adequate insurance cover. If the client doesn’t have the necessary insurances, the company usually increases the hire charge.
[edit] CPA Contract Lift
Clients who are inexperienced in hiring cranes and so do not have the necessary competencies for safe planning and use are able to make use of a CPA Contract Lift service. This means that the crane owner provides insurance cover and retains responsibility for the crane and other equipment, the operator and all other personnel supplied with the crane, as well as all aspects of the lift plan and execution.
It is important to note that a Contract Lift is only valid when the crane owner supplies the Appointed Person to supervise. The client retains certain liabilities and should hold insurance to protect against such things as their own negligence, poor ground conditions, or the supply of incorrect information regarding the lift.
[edit] Wind
According to LOLER, appropriate devices should be made available to detect dangerous situations and allow for effective mitigation in conditions of high wind that may threaten a crane and/or its load. The information regarding the maximum wind speed in which the crane can be safely operated should be known and made available.
It is also important that cranes are made safe during out-of-service periods. Foreseeable wind speeds should be analysed from historical data and local wind studies. This will influence the height as well as the size of the foundations, ballast and jib counterweights used.
[edit] Related articles on Designing Buildings Wiki
- Avoiding crane collapses.
- Banksman.
- Cherry pickers.
- Construction plant.
- Construction tools.
- Crane supports.
- Demolition.
- Demolition grapple market trends.
- Electromagnetic overhead cranes.
- Equipment in buildings.
- Health and Safety.
- Lifting Operations and Lifting Equipment Regulations (LOLER).
- Scaffolding.
- Site safety.
- Temporary works.
- Types of crane.
- Work at height.
- Work at height checklist for managers.
- Work at height regulations.
[edit] External references
Featured articles and news
Homes England supports Greencore Homes
42 new build affordable sustainable homes in Oxfordshire.
Zero carbon social housing: unlocking brownfield potential
Seven ZEDpod strategies for brownfield housing success.
CIOB report; a blueprint for SDGs and the built environment
Pairing the Sustainable Development Goals with projects.
Types, tests, standards and fires relating to external cladding
Brief descriptions with an extensive list of fires for review.
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.