Completion date in construction contracts
Most construction contracts set a date by which the works described in the contract must be completed (the completion date or contract completion date). This is not the date by which all obligations under the contract have to be discharged, but the date by which 'practical completion' must be certified. That is, the date by which the works have been completed and the client can take possession of the site, albeit there may be very minor items outstanding that do not affect beneficial occupancy by the client.
Certifying practical completion (referred to as 'substantial completion' on some forms of contract) returns possession of the site to the client, releases half of the retention, ends the contractor's liability for liquidated damages and signifies the beginning of the defects liability period. The defects liability period (sometimes called the rectification period) typically lasts six to twelve months during which the client may occupy the premises and the contractor must rectify any defects that are identified.
The completion date may be altered during the course of the contract, for example if the date the contractor takes possession of the site to begin construction is delayed, or if an extension of time is granted due to delays to the works that are not the contractor’s fault. Practical completion therefore must be certified by the most recently agreed completion date.
If practical completion is not certified by the most recently agreed completion date, then the contractor may be liable to pay liquidated and ascertained damages to the client. These are pre-determined damages set at the time that the contract is entered into, based on a calculation of the actual loss that the client is likely to incur if the contractor fails to meet the completion date. Some contracts require that a certificate of non-completion is issued as a pre-requisite to deducting liquidated and ascertained damages.
Where the contract requires sectional completion of the works, then separate dates for completion and separate rates of liquidated and ascertained damages should be set for each section.
NB: There can be a cascade effect, where delays in one section cause delays in another. The contractor may then be liable to pay liquidated and ascertained damages for each section.
On construction management contracts, a separate completion date must be set for each trade contract. Once all trade contracts have been certified as practically complete, the construction manager issues a certificate or project completion. The same is true on management contracts, where each works contract must be dealt with individually.
Documentation that should be issued to the client on certification of practical completion may include:
- A draft building owner's manual.
- A building user's guide.
- The health and safety file.
- The building log book.
- A construction stage report.
Notes:
- If a contract does not specify a completion date, then the works should be completed within a reasonable time, although it is unlikely that such an ambiguous arrangement would allow the client to deduct liquidated and ascertained damages.
- Construction contracts will generally include a provision requiring that the contractor proceeds ‘regularly and diligently’ irrespective of whether it is apparent that the completion date will be achieved.
- Practical completion is not a term recognised in some recently developed contacts such as PPC 2000 and other partnering contracts which simply refer to 'completion'. See Practical completion for more information.
- The 'contractor’s planned completion date' is the date shown on the contractor’s programme as being the date when the contractor plans to complete the works under the contract. This may be different to the contract completion date.
- The 'date for completion' is the date by which the contractor is expected to complete the works, which may be earlier or later than the contract completion date.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
See also: Failure to complete construction works.
[edit] Related articles on Designing Buildings
- Building completion.
- Certificate of non completion.
- Completion.
- Concurrent delay.
- Contractor’s planned completion date.
- Date for completion.
- Defects liability period.
- Extension of time.
- Failure to complete construction works.
- Final account.
- Final certificate.
- Handover to client.
- Liquidated and ascertained damages.
- Loss and expense.
- Migration strategy.
- Octoesse LLP v Trak Special Projects Ltd
- Practical completion.
- Progress of construction works.
- Sectional completion.
- Time at large.
- Topping out.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.