Commissioning building systems
Commissioning refers to the process of bringing an item into operation and ensuring that it is in good working order. On building projects, this refers primarily to building services.
When, after all or part of a fixed building service or on-site electricity generation system has been installed, replaced or altered, the system is taken from a state of static completion to working order. Testing and adjusting are carried out for fixed building services, as necessary, to ensure that the whole system uses no more fuel and power than is reasonable in the circumstances. Testing and adjusting are carried out for on-site electricity generation systems, as necessary, to ensure that the whole system produces the maximum amount of electricity that is reasonable in the circumstances For each system, commissioning includes all of the following.
|
Building services requiring commissioning may include:
- Heating, cooling and ventilation systems.
- Generators.
- Switchboards.
- Water supply and sanitation.
- Pumps.
- Motors.
- Fire detection and protection systems.
- Information and communications technology (ICT) systems.
- Security systems.
- Facilities management systems.
- Process plant.
- Lifting equipment and escalators.
- Acoustic and vibration appraisals.
The contract documents should set out:
- Who will be responsible for commissioning different building services.
- What methods, standards and codes of practice are to be used.
- What should happen to test results.
- Whether commissioning is to be witnessed and if so, whom.
- The documentation that is required.
Commissioning can benefit from the preparation of a commissioning plan, which according to BSRIA Guide BG 8/2009 Model Commissioning Plan should:
- Provide general information about the project.
- Identify the commissioning team members for each stage of the commissioning process.
- Define roles and responsibilities for each commissioning team member.
- Identify the systems to be commissioned.
- Create a schedule of commissioning activities for each stage of the process.
- Establish documentation requirements associated with the commissioning process.
A commissioning manager may be appointed to give advice during design, construction planning and installation and then to manage commissioning, testing and handover.
Commissioning activities may include:
- Ensuring client access and providing client training and demonstrations.
- Completing operating and maintenance manuals, record drawings, software and test certification.
- Obtaining statutory approvals and insurance approvals.
- Manufacturers work testing.
- Component testing.
- Pre-commissioning tests.
- Set to work: this is the process of switching on (i.e. setting to work) items such as fans and motors to ensure that they are operating as specified (for example checking that fans are turning the right way).
- Balancing: this follows setting to work and involves looking at whole systems (rather than individual components) to ensure that they are properly balanced (i.e. water is coming out of all the taps at the correct pressure, air is coming out of the correct diffusers, etc).
- Commissioning checks and performance testing.
- Post commissioning checks and fine tuning during occupancy.
NB: The building regulations require that a commissioning notice is given to the relevant building control body (BCB) confirming that commissioning has been carried out according to a procedure approved by the Secretary of State. See Commissioning notice for more information.
The BSRIA guide to 'Commissioning Air Systems' (BG 49/2024), written by by Keith Barker and published by BSRIA in March 2024, explains how to commission ducted air distribution systems in buildings. It was originally published in 2013, then 2015 with the latest update in 2024. For the benefit of the guide and number of commissioning relate terms arte defined, some of which are included here for information:
- Commissionable system: 'A system designed, installed and prepared to specified requirements in such a manner as to enable commissioning to be carried out'
- Commissionability: 'The ability of a system to be functionally tested and regulated satisfactorily'
- Commissioning: 'This is defined in CIBSE Code M[6] as "A process of assuring that a project is planned, programmed, costed, designed, installed, tested and fine-tuned, so it meets specified performance requirements".
- Commissioning management: 'The planning, monitoring and control of all aspects of commissioning and the engagement of all those involved in it, to achieve the specified outcomes.'
- Commissioning manager (CxM): 'The entity that leads the management of the commissioning process on a project.'
- Commissioning specialist: 'The organisation or person appointed to carry out specified duties in connection with functional testing and regulating of systems.'
- Commissioning specification: 'The document (or sub-section of the design specification) that prescribes the detailed objectives and requirements for commissioning Note: the specification should refer to drawings, schedules and relevant parts of the codes, manuals, guides and other standards.'
[edit] Related articles on Designing Buildings
- BREEAM seasonal commissioning.
- BSRIA Water Treatment for Closed Heating and Cooling Systems BG 50/2021.
- Client commissioning.
- Commissioning documents.
- Commissioning notice.
- Commissioning plan.
- Commissioning planning.
- Commissioning report.
- Commissioning v testing.
- Corrosion in heating and cooling systems.
- Handover to client.
- IAQ developments accelerated by COVID-19 pandemic.
- Initial commissioning case studies.
- Inspection.
- Migration strategy.
- Practical completion.
- Seasonal and continuous commissioning.
- Soft landings.
- Specialist commissioning manager.
- Training for pre-commissioning cleaning of pipework systems.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments