Last edited 13 Oct 2015

Design and build: mobilisation

RTENOTITLE

Mobilisation refers to the activities carried out after the client has selected the contractor, but before the contractor commences work on site. It is a preparatory stage during which the majority of activities are managed by the contractor.

We attribute the role of contract administrator to an 'employer's agent'. This role might be carried out by the client if they are experienced.

[edit] Preparing for the construction stage.

The employer's agent arranges a pre-contract meeting to discuss procedures that will be adopted during the construction stage.

There are a range of tasks necessary to prepare for the construction stage:

[edit] Mobilising.

Mobilising may involve the contractor carrying out the following tasks:

  • Arranging for production information to be issued for construction.
  • Co-ordinating the preparation and issue of a project handbook setting out responsibilities, procedures, and lines of communication for the construction stage.
  • Preparing method statements and obtaining method statements from sub-contractors such as demolition and groundwork sub-contractors.
  • Preparing a site layout plan for construction.
  • Placing sub-contracts.
  • Advertising and selecting catering, security and cleaning contracts as well as any direct labour requirements.
  • Establishing a contract register scheduling: the contracts which have been placed, who signed them and when, what the value of the contract is and where it is stored. This can be crucial information if for example the contractor becomes insolvent.
  • Establishing an asset register scheduling assets on site and who they belong to. This information may later be incorporated into the building owner's manual.
  • Establishing all statutory site registers such as; lifting equipment, dangerous and explosive substance storage, scaffolding and accident reports.
  • Managing specialist design and drawing approval. The contractor may wish to appoint a design co-ordinator to be responsible for this.
  • Complying with any statutory conditions that must be satisfied prior to construction (such as tree protection, submission of contaminated soil disposal plans, approval of work adjacent to an operating rail track and so on).
  • Ensuring (in their role as principal contractor) that workers are provided with suitable site induction, training and information to be able to work without undue risk to their health or safety.
  • Establishing inspection regimes and quality assurance procedures for construction.
  • Commissioning any further geotechnical survey work required.
  • If it has not already been done, obtaining statutory utility drawings of all existing and surrounding services including details of any telecoms, wells and hydraulic mains.
  • Arranging road closures and restrictions, diversions of services and connections necessary for the works to be carried out.
  • If it has not already been done, obtaining legal documentation describing precisely the site boundary and ownership.
  • Preparing (in their role as principal contractor) a construction phase plan, if this has not already been done.
  • Developing the site waste management plan (if required).
  • Commissioning a survey team to establish semi-permanent setting out theodolite base plates.
  • Arranging for the statutory utilities to provide the necessary water, power supplies, and ICT services required for construction activities.
  • Notifying the local authority (or approved inspector) of their intention to begin construction.
  • Informing the emergency services of their intention to begin construction.
  • Notifying the HSE if this has not already been done

outline plan | previous stage | next stage