Design and build: construction
During the construction stage the contractor takes possession of the site and carries out the construction works. Once the works are complete, a certificate of practical completion is issued and the site is handed back to the client.
Contents |
[edit] Starting the work stage.
The employer's agent arranges a handover meeting for the contractor to take possession of the site. See article handover to contractor.
Before work on site proceeds, the client and contractor confirm that that suitable welfare facilities have been provided by the contractor and the contractor (in their role as as principal contractor) confirms that a suitable construction phase plan has been prepared.
[edit] Construction.
The principal designer assesses and gives advice about any additional design information that is prepared by the contractor, specialist contractors or specialist designers (including temporary works) and the contractor updates the construction phase plan and re-issues it as required.
Where there are any proposed variations, procedures for their valuation are implemented (as described in the contract). Where changes exceed the delegated authority of the employer's agent, approval should be requested from the client.
The employer's agent co-ordinates site inspections, issues instructions as required and assesses any claims for extension of time or loss and/or expense (perhaps with advice from independent client advisers).
The contractor prepares interim applications for payment. The employer's agent checks applications for payment and issues payment notices to the contractor of the amount to be paid. The notices must be issued within five days of the dates for payment set out in the contract. If the client intends to pay less than the amount on the notices, pay less notices must be issued giving notice of the amount that will be paid and the basis for its calculation. The client then makes payments to the contractor by the final date for payment.
The employer's agent holds regular construction progress meetings and submits progress reports to the employer's agent. The employer's agent then prepares construction progress reports for the client.
[edit] Preparing for occupation.
If they have not already done so, the client begins preparations for occupation of the development, including the preparation of an operational policy and migration strategy setting out how they will manage the transition into and the operation of the new facility.
The client may have an 'occupation services contract' for delivering and installing equipment, fixtures and furniture (sometimes from other premises). This contract may also pick up small building changes that are considered too costly to be instructed under the main contract.
The client should ensure they have sufficient funds to release 50% of the retention upon certification of practical completion.
[edit] Inspections, commissioning and testing.
The client (generally representatives of the facilities management department) agrees procedures for inspections, commissioning, testing and client training with the contractor.
If it has not already been done, the client appoints an in-house or outsourced engineering team to witness testing and commissioning and to take over the running of the services as soon as practical completion is certified.
The client's engineering team co-ordinates procedures for inspections, commissioning, testing and client training in relation to building services and the client agrees procedures for inspections, commissioning, testing and client training in relation to other aspects of the building with the contractor.
The contractor rectifies any defects that become apparent during commissioning, testing and inspection procedures.
[edit] Practical completion.
The contractor prepares a draft building owner's manual, building log book and if required by the employer's requirements, a building user's guide. The principal designer completes the health and safety file.
The contractor confirms to the employer's agent that the works are complete.
The contractor arranges for final inspection of the works by the building control inspector (or approved inspector) and arranges for the issue of a building regulations completion certificate. NB Within 5 days of the completion of the building, the contractor must notify building control that the works have been carried out in accordance with the specification submitted with the building emission rate (BER) calculations, or the changes that have been made (see emission rates for more information).
The employer's agent arranges a handover meeting to handover the site to the client (see article handover to client).
The contractor prepares an interim application for payment, including the release of half the retention. The employer's agent checks application for payment and issues the certificate of practical completion and payment notice to the contractor of the amount to be paid. If the client intends to pay less than the amount on the notice, a pay less notice must be issued giving notice of the amount that will be paid and the basis for its calculation. The client makes payment by the final date for payment. This will include the release of 50% of the retention.
The employer's agent prepares and submits a construction stage report for the client. The client assesses the construction stage report, and gives instructions as necessary.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.