How much carbon are your buildings responsible for?
Contents |
[edit] Introduction
Carbon emissions must be reduced drastically if we are to limit global warming to safe levels. Construction is responsible for around 40% of global emissions.
[edit] Reducing embodied and whole-life carbon in buildings
Architectural Technologists are in a position to act positively on this issue by considering the whole life carbon footprint of the designs they develop and how the materials they specify perform in carbon terms.
[edit] Terminology
- Carbon (tCO2e): A simplified term used for describing greenhouse gas (GHG) emissions, measured in tonnes of carbon dioxide (CO²) equivalent. CO² is used as the metric as it is the most prevalent GHG, though it is worth noting that some other GHGs are more damaging to the climate, e.g. methane (CH4) which is at least 20 times as damaging as CO².
- Embodied carbon: The carbon expended in the production of a building, product or material. For a brick this would include the carbon emissions caused from quarrying raw material, transporting this to where it is processed and manufacturing into a useful product; all occurring before it arrives on your site ready for construction.
- Operational carbon: The carbon expended during operation, i.e. emissions caused by electricity and gas usage, plus refurbishment and/or replacement of materials over the life of a building.
- Whole life carbon: embodied carbon + operational carbon, measured over the buildings’ lifespan. This term takes into account all carbon expended over the life of a building from sourcing raw materials, their impacts in use to how those materials are likely to be treated at the end of their lifespan.
- Life cycle analysis (LCA): This is the process by which a carbon footprint is measured. LCAs to be used in BREEAM assessments usually assume a building lifespan of 60 years.
- Whole building life cycle analysis: The term used to specify that a life cycle assessment is covering a complete building design.
- Life cycle costing (LCC): This is the process for assessing how different design options will perform in cost terms over the buildings’ lifespan, considering their upfront, maintenance and replacement costs.
- Environmental product declaration (EPD certificate): Certification providing proof of the embodied carbon impacts of producing a material or component.
Figure 1: Stages considered in a life cycle carbon assessment. |
[edit] Guidance and legislation
A lot of changes have evolved in this area, including requirements around embodied carbon appearing in the New London Plan and many cities, regions and businesses adopting net-zero carbon targets. Here are some of the key updates.
Firstly, the RICS professional statement on whole life carbon calculation was released in 2017, standardising how carbon footprinting is carried out in the industry. This was much needed to allow safe and reliable comparisons to be made between buildings and for benchmarks to be developed and agreed upon across industry. Before this point, there was no agreed scope for life cycle assessments, leading to disparate and incomparable results.
Secondly, the 2018 version of BREEAM New Construction revised extensively how credits under the ‘Materials’ category are scored. For buildings aiming for high levels of attainment under BREEAM, carrying out LCA is now strongly encouraged.
References to the green guide to specification were removed and the scoring process heavily weighted towards carrying out life cycle analysis of design options, beginning at conceptual design stage. This has encouraged consideration of carbon impacts early in the design process when there is the best chance of making the design both carbon- and material-efficient.
[edit] Software tools
There are a range of tools available to aid in calculation and analysis of the whole life carbon impacts of buildings, including EC3, eTool, OneClick LCA and HBERT. OneClick and eTool are two commercially available tools approved by the BRE for use as part of BREEAM assessments (ref. BREEAM Mat01 tool v1.9).
A process for measuring and reducing whole building life cycle carbon footprints:
- Baseline calculation.
- Carbon hotspot analysis.
- Identify carbon reduction opportunities.
- Establish project reduction target.
- Refine opportunities.
- Incorporate opportunities into the design.
[edit] Carbon hotspots
Carbon hotspots are where the highest proportion of a buildings’ carbon footprint are found. These could be defined either by life cycle stage, building element or by material. The results of a recent carbon baselining exercise are presented in the following pie charts.
Figure 2: Carbon baseline figures by life cycle module. |
Figure 3: Carbon baseline materials hotspots. |
In this example, modules A1–A3 (Figure 2) were found to be the biggest life cycle stage carbon hotspot, and cement (Figure 3) was the biggest materials carbon hotspot. With this information, the design team could focus their carbon reduction efforts on their materials specification, developing low carbon opportunities and specifications, particularly for concrete elements.
[edit] Taking action
In summary, it is easier than ever to determine and act on the carbon footprint of designs. This is possibly the biggest opportunity for Architectural Technologists to make a positive contribution towards global decarbonisation efforts.
[edit] Rules of thumb
- Prioritise creative re-use, refurb and retrofit over new build. Retaining or reusing built elements avoids all carbon associated with demolition, transport and processing.
- Maximise structural efficiency. Adopting a lean design approach can drastically reduce materials quantities. We saved 1000 tonnes of steel from a railway station roof through additional analysis and design.
- Limit use of carbon-intensive materials. Use carbon-intensive materials where they are needed and of most use, but avoid them in any other situation.
- Use materials with high-recycled content. Recycled material is generally lower in carbon than virgin.
- Specify low-carbon concrete mixes. Use cement replacements wherever possible. We are specifying up to 70% cement replacement on several projects.
- Choose carbon sequestering materials. Use timber and other biological materials when possible.
This article originally appeared in the Architectural Technology Journal (at) issue 133 published by CIAT in Spring 2020. It was written by James Robb BSc (Hons) MCIAT
--CIAT
[edit] Related articles on Designing Buildings Wiki
- Architectural technologist.
- BREEAM UK New Construction 2018 changes summary.
- Carbon footprint.
- CIAT articles.
- Greenhouse gases.
- Life cycle in the built environment.
- Low carbon.
- Royal Institution of Chartered Surveyors RICS.
- Whole-life costs for buildings WLC.
- Wood, embodied carbon and operational carbon.
Featured articles and news
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..