Putting the benefits of infrastructure front and centre
The challenges of minimising the gap between what an infrastructure project is forecast to cost and what it will actually cost was the subject of discussion at an ICE and DfT roundtable in May 2019. |
Contents |
[edit] Introduction
In late May 2019, ICE and the Department for Transport (DfT) held an industry roundtable to discuss how infrastructure delivery can be improved, to more closely match estimates and outturns, while shining a spotlight on the benefits major projects bring. It was agreed that as long as margins remain thin, the sector will lack resources to improve through investment in innovation and skills.
Attendees also expressed concern that fixating on driving down upfront cost detracts from a more important focus on long-term thinking and achieving a much wider set of benefits from infrastructure networks.
[edit] ICE and DFT Reports
This discussion follows the release of two recent reports – ICE’s ‘Reducing the gap between cost estimates and outturns for major infrastructure projects and programmes’ and the DfT’s ‘Lessons from transport for the sponsorship of major projects'.
Both reports look at how delivery of major projects can be improved so that estimates more closely match final project costs, something crucial to maintaining confidence in how public money is spent.
DfT sets out five themes that encompass a total of 24 lessons learnt from major transport projects. These include the need to take ‘decisive action’ when schedule or cost tolerances are likely to be breached, or ensuring clear accountability for systems integration at the outset of a project.
ICE has taken evidence from leading sector and client organisations to identify and explain where the challenges are, set criteria to outline what a ‘good’ outcome is and map out actionable steps which can improve delivery.
[edit] The challenge with second-guessing the unknown
It is difficult to get the forecasting right on major infrastructure projects, and the further out from delivery a project is, the harder it becomes. Around the world, nine out of ten projects with a value of over $1bn go over budget or over deadline.
Hundreds, even thousands, of construction workers, engineers and multiple companies work together over years, if not decades, to deliver major projects. During this time, any number of factors can affect material costs, labour availability or the requirements a project needs to meet.
With a cost increase of nearly 270%, the London 2012 Olympic and Paralympic Games stand out as an example of the difficulties of forecasting. The 2005 estimate of £2.37bn ended up as a £8.77bn outturn – but there are two lessons to learn.
A recalculated budget in 2007, when exploration was complete, came in on target and the public consider the project a success – 74% say they would welcome the games back, and there was a £9.9bn boost to the economy.
Unforeseen circumstances and changing technology will affect projects. Who could have foreseen Brexit when Crossrail was given the go-ahead in 2007? Will planned road projects have to be redesigned to accommodate wireless re-charging or ensure connectivity for connected and autonomous vehicles?
[edit] Taking action and shifting the success narrative
Knowing the unknown is not something that can be easily planned for. What is in the control of project managers and policy makers is how they manage costs and improve processes. It is also crucial to re-define success to ensure the infrastructure we build retains value and realises the intended social, economic and environmental benefits.
A focus on outcomes receives public demand: 74% of GB adults told a YouGov poll for ICE that they want to hear more about the benefits of major infrastructure projects. The same poll found just 3% of GB adults think that the most important issue is that the overall cost of constructing a project is low, with 30% highlighting the need for communities to be regenerated.
ICE’s paper recognises the need for a shift in narrative, setting out that clients and the government should move away from lowest capital cost as the most important metric when assessing major projects. The focus must be on delivering infrastructure benefits, supported by a cost case which delivers the multipliers which underlined the project to begin with.
The paper also makes the case that completing scope, design and exploration before committing to work will help to avoid expensive retroactive changes. Making ‘should-cost’ modelling and other reforms set out in the Outsourcing Playbook mandatory would aid government clients in making better procurement decisions.
Finally, providing a cost estimate range, based on a should-cost model, would help to build-in flexibility to the budget and leeway to incentivise contractors who deliver below estimate.
[edit] Delivering for the public
Some say that the sector is losing the trust and confidence of key clients, including the government. That is a challenge the sector must take seriously, and it needs an appropriate response.
By focusing on the benefits infrastructure brings to communities, towns and cities, and taking a critical look at where the construction sector can improve, public confidence that they will get the infrastructure they need should start to improve.
[edit] About this article
This article was written by ice.org.uk Martin Shapland, Policy Manager at the Institution of Civil Engineers (ICE). It was originally published as a blog on the ICE website and can be accessed here.
[edit] Related articles on Designing Buildings Wiki
- Brexit - The case for infrastructure.
- Civil engineer.
- Community infrastructure levy.
- Government construction and infrastructure pipelines.
- Green infrastructure.
- Growth and Infrastructure Act.
- Hyperloop
- Infrastructure and Projects Authority.
- Infrastructure UK (IUK).
- Infrastructure nationalisation.
- London infrastructure plan.
- National Infrastructure Pipeline.
- National Infrastructure Plan.
- Nationally Significant Infrastructure Projects.
- Railway engineering.
- Smart cities.
- Traffic and transport.
Featured articles and news
Recharging Electrical Skills in Wales
Step by step collaborative solutions.
Ireland budget announcement 2025
CIOB responds with positivity, criticism and clarity.
The continued ISG fall out, where to go?
Support for ISG contractors, companies and employees.
New HES national centre for traditional building retrofit
Announced as HES publishes survey results which reveal strong support for retrofit.
Retrofit of Buildings, a CIOB Technical Publication
Expected to become one of the largest activities in the global construction industry.
Scope determination appeals and the Building Safety Act
Process explained following release of appeals guidance.
The ECA industry focus video channel
Keeping update with the industry session by session.
Over 25 recorded informations sessions freely available.
AT Awards 2024 ceremony East London October 25th.
Revisiting the AT community at the 2023 awards evening.
The Community Housing Fund and built affordable homes
CLTN reviews the impact of the Fund and calls for extension.
The grading system of the Regulator for Social Housing
A background, an explanation and ten recent enforcements.
Construction, repair and maintenance. Book review.
Putting new life into a city with a 1900 year history.
BSRIA Briefing 2024: Sustainable Futures speakers
Redefining Retrofit for Net Zero Living 22 Nov.
Wall of support for post-Grenfell regulation of electricians
Call for a shake-up of the construction industry highlighted on radio.
Digital sustainability through future AEC tools
Bringing together industry and academia to meet challenges.