Management contract: production information
This stage is concerned with preparing the information that the works contractors will need to construct the project. It should also include the completion of applications for statutory approvals. Within this plan the management contractor is appointed on completion of concept design. Earlier or later appointment will result in some activities being re-allocated between the consultant team and the management contractor (for example the role of cost consultant).
[edit] Starting the work stage.
The lead consultant co-ordinates a work stage start-up meeting with the client, management contractor and the consultant team to pass on feedback from the previous stage and agree the programme for the preparation of production information, along with its format, identification of any work packages, sequencing and co-ordination procedures, including co-ordinating and integrating information from specialist works contractors.
There should be a particular emphasis on equipment with long manufacturing times such as switchgear, chiller units, lifts, escalators and bespoke cladding systems, some of which may justify early ordering. The front-end construction work of service diversions, demolition, setting out, underground drainage, piling and groundworks may merit placing of preliminary contracts.
[edit] Agreeing tendering and construction procedures.
The management contractor instigates discussions with the client regarding tendering and construction. Discussions might include:
- The possible use of preliminary contracts (for works such as ground exploration, demolition, decontamination or site clearance).
- The possibility of ordering long-lead items (such as switchgear, transformers, or booking piling rigs).
- The form of contract and contract conditions for works contracts (if this has not already been agreed).
- The nature of warranties and performance bonds that will be required from works contractors.
- Exclusions from the contract.
- The date of possession and any phasing requirements.
- Tender procedures and the tender period.
- Any client contributions required for the contract documents.
- Insurance of the works.
- The need to appoint site inspectors.
- The need to appoint party wall surveyor(s) or rights of light surveyors.
[edit] Preparing production information and completing statutory approvals.
The lead designer prepares a schedule of production information, responsibilities for its preparation, a programme for its preparation and a document control system for version control.
The lead designer co-ordinates:
- The preparation and integration of production information. Any gaps in this information that will require specialist input after a tender process should be clearly defined, showing abutment details to adjacent work faces and how such work is integrated into the overall scheme.
- The preparation of schedules of inspections and tests, mock ups and samples.
- The preparation of a draft building user's guide and a building log book.
- The establishment of quality control systems and setting out criteria.
- Outstanding information needed for building regulations and other statutory approvals (such as negotiations with the Highways England, structural calculations, CO2 emission rate and a list of specifications used in the CO2 emission rate calculations) which must be submitted before works start on site.
The consultant team or management contractor may prepare or develop the site waste management plan if required.
The lead designer, consultant team and management contractor undertake a design review of the production information and make amendments or additions as necessary.
The management contractor develops the draft preliminaries document, draft tender documents and proposed contract conditions for the works contracts (including relevant pre-construction services) and assesses any changes relative to the approximate quantities cost plan.
The lead consultant co-ordinates the preparation of a production information report for the client including any remaining components, assemblies, specialist items, samples or materials still requiring approval by client.
The management contractor and client should ensure that relevant party wall notices have been served.
The client considers the production information report and if necessary issues instructions to the lead consultant regarding changes required.
Featured articles and news
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Digital technology, transformation and cybersecurity
Supporting SMEs through Digitalisation in Construction.
Villa Wolf in Gubin, history and reconstruction. Book review.
Construction contract awards down one billion pounds
Decline over the past two months compared to the same period last year, follows the positive start to the year.
Editor's broadbrush view on forms of electrical heating in context.