Production information report for design and construction
The production information report is a work stage report produced by the consultant team for the client at the end of the production information stage (see free work plans on the Designing Buildings Wiki home page).
It is the last opportunity for the client to consider issues to do with the design of the development and the form of contract before the tender process begins. It may also be the first time that the client has seen drawings describing key components (such as door handles), assemblies and specialist items. As a result, the client may wish to issue the production information report (or parts of it) for consideration to key users (or user panels) and perhaps to their lawyer or other independent client advisers. Once the main contractor has been appointed, subsequent changes can become very expensive.
The production information report may include:
- The approximate quantities cost plan and cash flow projection.
- Packaging strategy (and costs associated with individual packages).
- An assessment of cost uncertainty and the reasons for this.
- Identification of provisional sums.
- A schedule of outstanding information (including any client contributions that will be required for the contract documents).
- A schedule of outstanding consents (such as statutory approvals or planning conditions).
- A description of proposed preliminaries and other items to bring to the client's attention.
- Proposed warranties and bonds.
- The proposed form of contract, contract conditions and any proposed changes to the contract.
- Proposed treatment of liquidated damages.
- A schedule of exclusions from the contract.
- Any insurance issues.
- Drawings and specifications describing key components, assemblies and specialist items.
- A list of any remaining components, assemblies, specialist items, samples or materials still requiring approval by client.
- An assessment of the possible use of preliminary contracts.
- An assessment of the possibility of ordering long-lead items early.
- The proposed date of possession.
- Tender procedures and the tender period.
- An assessment of the need to appoint site inspectors.
- An assessment of the need to appoint party wall surveyor(s).
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
New guidance for professional practice, cultural change and regulation in social housing.
The heritage of nuclear and conventional power stations.
New measures to stop people being ripped off
Government to protect families from cowboy builders and aggressive bailiffs.
New Futurebuild showcase brings an innovation-first approach.
National Planning Policy Framework
Understanding the 2026 changes.
ECA's public affairs priorities
Member consultation opens to shape priorities for 2027 to 2030.
Dutyholder responsibilities from 1 July 2026.
Where performance meets practice
The Building Envelope Stage at UKCW Birmingham.
CIAT publishes briefing on planning reforms.
Leaders in Learning for Practice Network
Call for conservation leaders in learning to register interest in new network.
The importance of early engagement
Construction lessons from the Trillium HealthWorks Experience Centre.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.


















Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.