Cost certainty
For clients and contractors in the construction industry, cost certainty is one of the most important performance criteria. It has a direct impact on resources.
Cost certainty is the likelihood that before a project, or part of a project starts, it will be completed within the agreed budget. Cost certainty is affected by time certainty which is the likelihood that a project, or part of a project, will be completed within the agreed time period agreed.
Construction clients often hold these two concepts as their top priorities as delays and cost overruns can be disastrous. It is for this reason that clients will tend to hold a contingency fund to deal with unforeseen eventualities.
For contractors, it may mean lower than expected profits as a result of:
- Increases in overheads.
- Hiring more operatives.
- Longer plant-hire periods.
- Storage of materials costs.
- Delayed payments from the client.
Some factors that cause delays and cost overruns may not be the contractor's fault:
- Clients making changes.
- Unforeseen ground conditions.
- Delays in material or equipment supplies.
- Inclement weather.
- Labour disputes.
- Changes in market conditions.
However, a 1996 study by the Construction Industry Board (CIB) revealed that cost and time certainty is more often than not under the contractor’s control, resulting from:
- Poor management.
- The contractors’ inability to predict and control the time needed to complete a project.
- Inaccurate material estimating.
- Poor productivity.
- Inadequate planning.
- Poor site management.
Clients will tend to have more confidence in contractors who have a solid record of reliability when it comes to cost certainty and so are likely to rate highly.
Cost certainty tends to improve as a project progresses, as some of the works are complete, and so their actual cost is known, and some risks may have been avoided or mitigated. It is for this reason that the client may reduce the amount they hold as contingency as the project proceeds.
[edit] Related articles on Designing Buildings Wiki
- Budget.
- Capital costs.
- Construction costs.
- Construction price and cost indices.
- Cost-benefit analysis in construction.
- Cost control.
- Cost engineering.
- Cost information.
- Cost of building.
- Cost overruns.
- Cost plans.
- Cost vs price.
- Front-loaded costs.
- Estimate.
- Hard costs v soft costs.
- Irrelevant cost.
- Life cycle assessment.
- New Rules of Measurement.
- Operational costs.
- Other development/project costs.
- Quantity surveyor / Cost consultant.
- Relevant cost.
- Whole life cost.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.