Beam and block floor construction
Contents |
[edit] Introduction
Beam and block is also referred to in some countries as ‘rib and block’ or ‘lintel and block’. The technique is used to create in-situ, suspended concrete floors (ground or upper) in concrete or masonry buildings and has become popular in residential construction.
[edit] Composition
Beam and block floors incorporate clay or concrete blocks, either solid or hollow (sometimes referred to as ‘pots’), supported on a series of parallel, typically pre-cast, pre-stressed concrete beams or ribs. Once the blocks are placed to infill between the parallel concrete beams, a continuous working surface is created.
There are several ways to achieve this. One involves inverted T-beams that incorporate continuous ledges on their lower sections that give the blocks full support. Beams are typically 130-250mm-deep and can be made to span up to 6m. The beam profile will depend on the span, the shape of the block and the loading requirements.
With the beams in place and supported at either end, laying the infill blocks is a quick process: assuming the blocks are to hand, a worker can drop one into place every five to ten seconds. A typical current block specification is to have dimensions of 440 x 215 x 100mm thickness, 3.5N/mm2 or 7N/mm2 minimum compressive strength, and able to support a minimum transverse load of 3.5kN on a 420mm span.
The advantage of beam and block is that no shuttering (support) is required on the underside of the floor as the beams are supported at each end, either on internal load bearing walls or on perimeter walls. Once the filler blocks are installed, a continuous working surface is created upon which further work can take place safely. Often, a sand and cement grout is brushed over the top surface to fill any gaps and prevent insects and vermin from entering, as well as to assist with air tightness.
[edit] Choice of floor finish
This may be followed by either timber deck flooring (eg flooring grade OSB, ply, etc) or a poured structural concrete topping (or screed). Alternatively, insulation slabs may be laid over a beam/block floor followed by a damp-proof membrane (if it is a ground floor) or vapour barrier followed by the structural concrete topping. The topping may also incorporate steel mesh reinforcement for greater strength. Once cured, the topping will allow the floor to take its full working load.
Precast beams are very popular as they allow the floor to be assembled relatively quickly to create a usable working platform. The beam’s cross-section can vary and will depend on the manufacturer. It will also determine the resulting soffit which will either be closed, in which case a relatively continuous soffit will be produced, or it will be open and will require an applied ceiling: this might be plaster or enclosure by a suspended ceiling.
Where a very lightweight, insulated floor slab is required, the concrete hollow blocks can be replaced with rigid insulation slabs.
[edit] Advantages and disadvantages
The advantages of beam and block floors are:
- Easy to handle
- Can make use of unskilled labour
- Provide a durable concrete floor system
- Can be used for suspended ground and upper floors
- Economical due to the off-site manufacture of beams and blocks
- Hollow blocks give a lighter construction than in situ-poured concrete slabs and can be quicker as they do not rely on the curing time for a poured concrete slab
- Can be used for suspended floors just above the ground where, for example, the site slopes; the ground has poor bearing capacity; there is a high water-table or toxic chemicals are present in the ground.
- Can reduce site delays as the method is not weather dependent.
- Provides good fire resistance and noise reduction
- Shuttering is not normally required.
- Hollows can be used for running services such as underfloor heating.
Disadvantages include:
- Not suited to irregular plan shapes that require a large number of special-shaped units: the key to economy is standardisation
- Can be difficult to provide a monolithic structure, as providing an efficient, rigid junction between the floor and the supporting beams or walls may be problematic.
Image courtesy of Forterra Building Products
[edit] Related articles on Designing Buildings Wiki
- Blinding.
- Coal holes, pavement lights, kerbs and utilities and wood-block paving.
- Compartment floor.
- Floating floor.
- Floor definition.
- Floor insulation.
- Floor loading.
- Flooring defects.
- Floors of the great medieval churches.
- Insulation for ground floors.
- Plenum.
- Raised floor.
- Separating floor.
- Sistering floor joists.
- Slab.
- Sprung floor.
- Suspended ceiling.
- Suspended timber floor.
- Types of flooring.
[edit] External references
- ‘Building Construction Handbook’ (6th ed.), CHUDLEY, R., GREENO, R., Butterworth-Heinemann (2007).
- Forterra Building Products Ltd
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.