Material procurement
Procurement is a term describing the purchasing process for goods and services. In building construction, material procurement is the process by which the materials required to construct a building are selected, ordered, invoiced, paid for and delivered to the site.
A procurement team, or one or more construction buyers may be responsible for procurement activities for products, materials, plant and subcontractors. They typically work for the main contractor(although sub-contractors may also have buyers on large projects) to ensure that supplies are provided in accordance with the project programme, specification and budget. For more information see: Construction buyer
Materials will typically be ordered from the supply chain, often from external suppliers with whom the team may have had past successful dealings, or who may be specified in the contract documents.
Procuring materials is a crucial aspect of the construction process as contractors will normally be inundated with requests from suppliers for the provision of goods and services. They must therefore order materials that align with both the client’s and contractor’s objectives.
Developing the most suitable purchasing strategy will involve selecting material suppliers according to a range of criteria that are likely to include speed of delivery, cost, quality, specific project constraints, risk, asset ownership and financing.
Within a specification, buyers may have flexibility in purchasing, particularly where an architect or engineer has specified a product and added the clause ‘…or equal approved’, upon which the buyers may – for good reason – substitute a different product that must, as a minimum, meet the same standards as the original.
Where a specification stipulates only one type or brand of material/product available from one supplier, the procurement team may be bound to procure that product even though it may consider that there are better equivalent offers on the market.
[edit] Competitive bidding
Suppliers of goods may be selected from a list of registered suppliers of the product/material to be purchased. Selection may be on the basis of a competitive tender, where selected suppliers must submit their most competitive price for the item in question. In some cases, a supplier may be specified on the basis of criteria such as product patent and/or uniqueness of offer.
[edit] Sustainability
In recent years, sustainability has assumed growing importance in the procurement of construction materials, particularly as they are the largest single category of waste going to landfill, and the industry is one of the largest producers of CO2 emissions. Local councils, clients and contractors may influence procurement by, for example, stipulating a minimum percentage of recycled materials must be used.
Whether in the specification or not, procurement teams will usually endeavour to source the most environmentally friendly options combined with value for money. This is particularly important in the light of the 2006 definition of sustainable procurement by the Sustainable Procurement Task Force: ‘A process whereby organisations meet their needs for goods, services, works and utilities in a way that achieves value for money on a whole-life basis in terms of generating benefits not only to the organisation, but also to society and the economy, while minimising damage to the environment.’
So, sustainable procurement assesses value for money in terms of the wider benefits to society, the economy and the environment as well as the narrower benefits of the procuring organisation. This might include consideration of lifecycle impacts, environmental impacts and social impacts. These extrinsic cost considerations are factored into decisions alongside the conventional procurement criteria which have tended to focus on price, quality and time.
In construction, sustainable procurement might involve consideration of the environmental, social and economic consequences of: :
- Design.
- Non-renewable material use.
- Manufacture and production methods.
- Logistics.
- Service delivery.
- Building use and operation.
- Maintenance and repairs.
- Reuse and recycling options.
- Disposal.
Click here for further information on sustainable procurement.
[edit] Related articles on Designing Buildings Wiki
- BREEAM Responsible sourcing of materials.
- Construction buyer.
- Cost led procurement.
- Environmental plan.
- Green Seal.
- Managing the procurement process.
- Procurement route.
- Public procurement.
- Recyclable construction materials.
- Sustainable development.
- Sustainable materials.
- Sustainability.
- Whole life costs.
- Design and build procurement route
- Engineering procurement and construction contract
- Managing the procurement process
- OJEU procurement procedures
Featured articles and news
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
Comments